he following information applies to the questions displayed
below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,291,000 | $ | 3,555,000 | $ | 2,259,400 | |||
Estimated costs to complete as of year-end | 5,609,000 | 2,054,000 | 0 | ||||||
Billings during the year | 2,110,000 | 3,736,000 | 4,154,000 | ||||||
Cash collections during the year | 1,855,000 | 3,500,000 | 4,645,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
2-a. In the journal below, complete the
necessary journal entries for the year 2021 (credit "Various
accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2022 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2023 (credit "Various accounts" for
construction costs incurred).
Solution:
Workings are given at the end of the solution.
a. Journal entries for 2021:
2021 | ||
Debit | Credit | |
Construction in progress | 2,291,000 | |
Various accounts | 2,291,000 | |
To record construction costs | ||
Accounts receivable | 2,110,000 | |
Contract Billings | 2,110,000 | |
Recording Progress billings | ||
Cash | 1,855,000 | |
Accounts receivable | 1,855,000 | |
Recording Collections | ||
Work in Progress | 609,000 | |
(gross profit) | ||
Construction Costs | 2,291,000 | |
(cost incurred) | ||
Income (Revenue) from long-term contracts | 2,900,000 | |
Recording Gross Profit |
b. Journal Entries for 2022:
2022 | ||
Debit | Credit | |
Construction in progress | 3,555,000 | |
Various accounts | 3,555,000 | |
To record construction costs | ||
Accounts receivable | 3,736,000 | |
Contract Billings | 3,736,000 | |
Recording Progress billings | ||
Cash | 3,500,000 | |
Accounts receivable | 3,500,000 | |
Recording Collections | ||
Work in Progress | 945,000 | |
(gross profit) | ||
Construction Costs | 3,555,000 | |
(cost incurred) | ||
Income (Revenue) from long-term contracts | 4,500,000 | |
Recording Gross Profit |
c. Journal entries for 2023:
2023 | ||
Debit | Credit | |
Construction in progress | 2,259,400 | |
Various accounts | 2,259,400 | |
To record construction costs | ||
Accounts receivable | 41,54,000 | |
Contract Billings | 41,54,000 | |
Recording Progress billings | ||
Cash | 4,645,000 | |
Accounts receivable | 4,645,000 | |
Recording Collections | ||
Work in Progress | 340,600 | |
(gross profit) | ||
Construction Costs | 2,259,400 | |
(cost incurred) | ||
Income (Revenue) from long-term contracts | 2,600,000 | |
Recording Gross Profit |
Workings:
Computation of Revenue:
2021: $2,291,000
= 29.0% × $10,000,000 = $2,900,000
$7,900,000
2022: $5,846,000
= 74.0% × $10,000,000 – 2,900,000 = $4,500,000
$7,900,000
2023: $10,000,000 – 7,400,000 = $2,600,000
Computation of Gross profit (loss):
2021: $2,900,000 – 2,291,000 = $609,000
2022: $4,500,000 – 3,555,000 = $945,000
2023: $2,600,000 – 2,259,400 = $340,600
he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...
The following information applies to the questions displayed below.) In 2021. the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate...
(The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate recognizes revenue over time according to percentage of completion. 3....
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 2023 $2,259,400 0 4,154,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000 3,500,000 4,645,000 Westgate...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,204,000 5,396,000 2,140,000 1,870,000 2022 $3,192,000 2,204,000 3,256,000 3,200,000 4,604,000...