Question

Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Price 10000000 10000000                        1,00,00,000
2021 2022 2023
Cost to date 2291000 6146000 9401000
Estimated cost to complete 5609000 3155000 0
Progress billing to date 2110000 3736000 4154000
Estimated total cost         79,00,000                          93,01,000                           94,01,000
Estimated gross profit        21,00,000                            6,99,000                             5,99,000
a) Percentage of completion Caln
Gross Profit recognized in 2021           6,09,000 (2291000/7900000*2100000)
Loss recognized in 2022         -1,47,108 (6146000/9301000)*699000-609000
Loss recognized in 2022           1,37,108 (599000-609000+147108)
b) Percentage of completion Caln
Revenue recognized in 2021         29,00,000 (2291000/7900000*10000000)
Revenue recognized in 2022         37,07,892 (6146000/9301000)*10000000-2900000
Revenue recognized in 2022         33,92,108 (10000000-2900000-3707892)
Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following information applies to the questions displayed below.) In 2021. the Westgate Construction Company entered...

    The following information applies to the questions displayed below.) In 2021. the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate...

  • Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...

  • (The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    (The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate...

  • he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate recognizes revenue over time according to percentage of completion. 3....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:                                      2018                         2019                            2020 Cost incurred during the year    $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end         5,609,000 2,054,000 0 Billings during the year    2,110,000               3,736,000                   4,154,000 Cash collections during the year                            1,855,000    3,500,000 4,645,000 Westgate...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 2023 $2,259,400 0 4,154,000...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT