Question

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

                                     2018                         2019                            2020

Cost incurred during the year    $ 2,291,000 $ 3,555,000 $ 2,259,400

Estimated costs to complete as of year-end         5,609,000 2,054,000 0

Billings during the year    2,110,000               3,736,000                   4,154,000

Cash collections during the year                            1,855,000    3,500,000 4,645,000

Westgate recognizes revenue over time according to percentage of completion. rev: 09_15_2017_QC_CS-99734 Required:

1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years

                                          2018   2019     2020

Revenue:

Gross profit:

0 0
Add a comment Improve this question Transcribed image text
Answer #1

2018

2019

2020

Contract price

10,000,000

10,000,000

10,000,000

Actual costs to date

2,291,000

5,846,000

8,105,400

Estimated costs to complete

5,609,000

2,054,000

0

Total estimated costs

7,900,000

7,900,000

8,105,400

Estimated gross profit (loss) {actual in 2020}

2,100,000

2,100,000

1,894,600

Revenue recognition using

= {actual costs to date/total estimated costs * contract price} – revenue recognized till            date

2018 = 2291000/7900000 * 10,000,000 = $2,900,000

2019 = {5846000/7900000 * 10,000,000} – 2900,000 = $7,400,000 -2,900,000 = $4,500,000

2020 = 10,000,000 – (2900,000 + 4500,000) = $2,600,000

Similarly, Gross profit (loss) recognition using percentage of completion method as

2018 = 2291000/7900000 * 2,100,000 = $609,000

2019 = {5846000/7900000 * 2100,000} – 609000 = 1554000 – 609000 = $945000

2020 = 1894600 – 1554000 = $340,600

Add a comment
Know the answer?
Add Answer to:
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate recognizes revenue over time according to percentage of completion. 3....

  • Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...

  • The following information applies to the questions displayed below.) In 2021. the Westgate Construction Company entered...

    The following information applies to the questions displayed below.) In 2021. the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate...

  • (The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    (The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate...

  • Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...

  • he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...

  • in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,074,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,542,000 5,658,000 2,020,000 1,810,000 2019 $3,772,000 1,886,000 4,294,000 3,800,000 3,686,000 4,390,000 Westgate recognizes revenue over time according to percentage of completion....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000 Westgate recognizes revenue over time according to percentage of completion....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT