Question


In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Contract price $10,000,000
2018 2019 2020
Cost incurred during the year $2,542,000 $3,810,000 $3,210,000
Cumulateive cost incurred $2,542,000 $6,352,000 $9,562,000
Estimated cost to complete as of year-end $5,658,000 $3,110,000 $0
$8,200,000 $9,462,000 $9,562,000
% of completion(cumulative) 31.00% 67.13% 100.00%
2018 2019 2020
Revenue(Cumulative) $3,100,000 $6,713,168 $10,000,000
Revenue per year $3,100,000 $3,613,168 $3,286,832
Cost incurred $2,542,000 $3,810,000 $3,210,000
Gross profit $558,000 -$196,832 $76,832

*If you face any difficulty please let me know in the comment section. Please give your valuable feedback.

Add a comment
Know the answer?
Add Answer to:
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa ...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...

  • In 2018, the West $10,000,000. gate Construction Company entered into a contract to construct a road...

    In 2018, the West $10,000,000. gate Construction Company entered into a contract to construct a road for Santa Clara County for The road was completed in 2020. Information related to the contract is as follows: 2020 2018 2,542,000 $3,772,000 $2,074,600 5, 658,000 1,886,000 2,020,000 4,294,000 3,686,000 1,810,000 3,800,000 4,390,000 2019 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of...

  • 0 Required information The following information applies to the questions displayed below In 2018, the Westgate...

    0 Required information The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 2019 $2,542,000 $3,772,000 $2,074,600 1,886, 000 2,020,000 4,294,000 3,686,000 1,810,000 3,800,000 4,390,000 2018 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the...

  • 0 Required information The following information applies to the questions displayed below In 2018, the Westgate...

    0 Required information The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 2019 $2,542,000 $3,772,000 $2,074,600 1,886, 000 2,020,000 4,294,000 3,686,000 1,810,000 3,800,000 4,390,000 2018 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the...

  • The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered...

    The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2019 $2,542,000 3,772,000 $2,074,600 1, 886,000 2,020,000 ,294,000 3,686,000 1,810,000 3, 800,000 4,390,000 2018 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 5,658,000...

  • 0 Required information The following information applies to the questions displayed below In 2018, the Westgate...

    0 Required information The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2019 $2,542,000 $3,772,000 $2,074,600 1,886,000 2,020,000 4,294,000 3,686,000 1,810,000 3, 800,000 4,390, 000 2018 2020 Lnurred uing ete as of year-nd 00 .2400 1390,000 Estimated costs to complete as of year-end Billings during the...

  • Required information [The following information applies to the questions displayed below. In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below. In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows 2019 $2,542,000 $3,772,000 $2,074,600 1,886,000 2,020,000 4,294,0003,686,000 1,810,000 3,800,000 4,390,000 2018 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 5,658,000 Westgate...

  • The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered...

    The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for 10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 2019 2,542,000 $3,772,000 $2,074,600 1,886,000 2,020,000 4,294,000 3,686,000 1,810,000 3,800,000 4,390,000 2018 Cost incurred during the year Estimated costs to complete as of year-end Billinga during the year Cash collections during the year 5, 658,000 Westgate...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000 Westgate recognizes revenue over time according to percentage of completion....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:                                      2018                         2019                            2020 Cost incurred during the year    $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end         5,609,000 2,054,000 0 Billings during the year    2,110,000               3,736,000                   4,154,000 Cash collections during the year                            1,855,000    3,500,000 4,645,000 Westgate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT