Question

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred). 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2021 2022 2023 Cost incurred during the year $ 2,510,000 $ 3,855,000 $ 3,210,000 Estimated costs to complete as of year-end 5,710,000 3,210,000 0 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2021 2022 2023 Cost incurred during the year $ 2,510,000 $ 3,855,000 $ 4,065,000 Estimated costs to complete as of year-end 5,710,000 4,210,000 0

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1 Under completed contract method,Gross profit is recognized in the year of completion of contract
However,losses will be recognized when the cost incurred and estimated cost exceeds contract price,
For 2021
Revenue recognized=0.
Gross profit recognized=0
For 2022
Revenue recognized=0.
Gross profit recognized=0
For 2023
Revenue recognized=$ 100000000
Gross profit recognized:
$
Contract price 10000000
Less: Cost incurred (2291000+3555000+2259400) 8105400
Gross profit recognized 1894600
2a. No. Year General journal Debit Credit
1 2021 Construction in progress 2291000
Various accounts 2291000
(Cost incurred)
2 2021 Accounts receivable 1900000
Billings on construction contract 1900000
(Billings made during the year)
3 2021 Cash 1700000
Accounts receivable 1700000
(Cash received from customers)
2b. No. Year General journal Debit Credit
1 2022 Construction in progress 3555000
Various accounts 3555000
(Cost incurred)
2 2022 Accounts receivable 3946000
Billings on construction contract 3946000
(Billings made during the year)
3 2022 Cash 3500000
Accounts receivable 3500000
(Cash received from customers)
2c. No. Year General journal Debit Credit
1 2023 Construction in progress 2259400
Various accounts 2259400
(Cost incurred)
2 2023 Accounts receivable 4154000
Billings on construction contract 4154000
(Billings made during the year)
3 2023 Cash 4800000
Accounts receivable 4800000
(Cash received from customers)
4 2023 Billings on construction contract 10000000
Construction contract revenue 10000000
(Revenue recognized)
5 2023 Cost of construction (2291000+3555000+2259400) 8105400
Construction in progress 8105400
(Contract cost recognized)
3 Balance sheet
At December 31,2021
$ $
Current asset:
Accounts receivable (1900000-1700000) 200000
Cost in excess of billings
Cost incurred 2291000
Less: billings 1900000 391000
Current liabilities: 0

Add a comment
Know the answer?
Add Answer to:
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,975,000 $ 3,825,000 $ 1,870,000 Estimated costs to complete as of year-end 5,525,000 1,700,000 0 Billings during the year 2,500,000 4,300,000 3,200,000 Cash collections during the year 2,300,000 4,100,000 3,600,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,849, eee Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,072,00 5,328,000 2,160, eee 1,880, eee 2022 $2,738,000 2,590,000 2,650, eee 2,700,eee 5,190, eee 5,420, eee Westgate recognizes revenue over time...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 4....

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,550,000 $4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during the year 2,050,000 4,750,000 3,200,000 Cash collections during the year 1,825,000 4,100,000 4,075,000 Westgate recognizes revenue over time according to percentage of...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 2023 $2,008,600 0 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT