In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
2021 | 2022 | 2023 | |||||||||
Cost incurred during the year | $ | 3,471,000 | $ | 4,005,000 | $ | 1,566,400 | |||||
Estimated costs to complete as of year-end | 5,429,000 | 1,424,000 | 0 | ||||||||
Billings during the year | 2,900,000 | 4,576,000 | 2,524,000 | ||||||||
Cash collections during the year | 2,700,000 | 4,500,000 | 2,800,000 | ||||||||
Assume that Westgate Construction’s contract with Santa Clara
County does not qualify for revenue recognition over time.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary
journal entries for the year 2021 (credit "Various accounts" for
construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2022 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2023 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to
prepare a partial balance sheet for 2021 and 2022 showing any items
related to the contract.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
2021 | 2022 | 2023 | |||||||||
Cost incurred during the year | $ | 2,490,000 | $ | 3,845,000 | $ | 3,290,000 | |||||
Estimated costs to complete as of year-end | 5,690,000 | 3,190,000 | 0 | ||||||||
5. Calculate the amount of revenue and gross profit (loss)
to be recognized in each of the three years assuming the following
costs incurred and costs to complete information.
2021 | 2022 | 2023 | |||||||||
Cost incurred during the year | $ | 2,490,000 | $ | 3,845,000 | $ | 4,035,000 | |||||
Estimated costs to complete as of year-end | 5,690,000 | 4,190,000 | 0 | ||||||||
Ans1] Amount of revenue and gross profit tobe recognised each year is as follows ---
Particulars | 2021 | 2022 | 2023 |
Cash collection during the year | 2700000 | 4500000 | 2800000 |
Revenue recognised each year *[A] | 0 | 0 | 10000000 |
Cost incurred each year | 3471000 | 4005000 | 1566400 |
Total Cost[B] | 9042400 | ||
Gross Profit[+]/Loss[-]* [A-B] | 0 | 0 | 958000 |
As it is given that the contract does not qualify for revenue recognition over time , the cash collections during the year were not rcognised as revenue for the year.In the year 2023 revenue and costs are recognised as the contract obligation is satisfied.
Ans 2 a],b],c]
Date | Particulars | Debit $ | Credit$ | |
2021 a |
Bank A/c To Deferred Revenue |
2700000 | 2700000 | |
Prepaid Conntract Cost To Various Accounts |
3471000 | 3471000 | ||
2022 b |
Bank A/c To Deferred Revenue |
4500000 | 4500000 | |
Prepaid Conntract Cost To Various Accounts |
4005000 | 4005000 | ||
2023 c |
Bank A/c To Deferred Revenue |
2800000 | 2800000 | |
Prepaid Contract Cost To Various A/cs |
1566400 | 1566400 | ||
Billing To Excess Billig |
958000 | 958000 |
Ans 3
In partial balance sheet for 2021 &2022 we have to show cash receipts received during th e year and excess billing if any.
Liabilities | 2021 | 2022 |
Deferred Revenue | 2700000 | 4500000 |
Excess Billing | 0 | 0 |
Ans 4
Particulars | 2021 | 2022 | 2023 |
Revenue[a] | 10000000 | ||
Cost icurred each year | 2490000 | 3845000 | 3290000 |
Cost recognised[b] | 0 | 0 | 9625000 |
Gross Profit[+]Loss[-][a-b] | 375000 |
Ans 5
Particulars | 2021 | 2022 | 2023 |
Revenue[a] | 10000000 | ||
Cost icurred each year | 2490000 | 3845000 | 4035000 |
Cost recognised[b] | 0 | 0 | 10370000 |
Gross Profit[+]Loss[-][a-b] | -370000 |
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,975,000 $ 3,825,000 $ 1,870,000 Estimated costs to complete as of year-end 5,525,000 1,700,000 0 Billings during the year 2,500,000 4,300,000 3,200,000 Cash collections during the year 2,300,000 4,100,000 3,600,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 4....
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 2023 $2,008,600 0 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. Problem...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008, 600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion....
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...