In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000
Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time.
Required:
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years
2-a. In the journal below, complete the necessary journal entries for the year 2021(credit "Various accounts for construction costs incurred)
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts for construction costs incurred)
3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information 2021 2022 2823 Cost incurred during the year $2,550,000 $3,875,000 $3,250,000 Estimated costs to complete as of a year and 5,75e.ee 3.250.000
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.
Cost incurred during the year Estimated costs to complete as of year-end 2821
$2,550,000 5,750,000 2022 $3,875, eee 4,25e,eee 2823 $4,125, eee
Answer 1
Answer 1 | |||
Year | 2021 | 2022 | 2023 |
Cost incurred during the year | $ 1,875,000 | $ 3,375,000 | $ 2,475,000 |
Cumulative cost incurred at end of year | $ 1,875,000 | $ 5,250,000 | $ 7,725,000 |
Cumulative cost incurred at end of year | $ 1,875,000 | $ 5,250,000 | $ 7,725,000 |
Add: Estimated costs to complete as of year-end | $ 5,625,000 | $ 2,250,000 | $ 0 |
Total estimated cost | $ 7,500,000 | $ 7,500,000 | $ 7,725,000 |
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) | 25.00% | 70.00% | 100.00% |
Revenue recognized till the date (10000000 * percentage of completion) | $ 2,500,000 | $ 7,000,000 | $ 10,000,000 |
Less: Revenue recognized up to earlier year | $ 0 | $ 2,500,000 | $ 7,000,000 |
Revenue recognized in current year | $ 2,500,000 | $ 4,500,000 | $ 3,000,000 |
Revenue recognized in current year | $ 2,500,000 | $ 4,500,000 | $ 3,000,000 |
Less: cost incurred during the year | $ 1,875,000 | $ 3,375,000 | $ 2,475,000 |
Gross Profit (Loss) | $ 625,000 | $ 1,125,000 | $ 525,000 |
Your Answer | |||
Year | 2021 | 2022 | 2023 |
Revenue | $ 2,500,000 | $ 4,500,000 | $ 3,000,000 |
Gross Profit (Loss) | $ 625,000 | $ 1,125,000 | $ 525,000 |
Answer 2 and 3
Answer 4
Answer 4 | |||
Year | 2021 | 2022 | 2023 |
Cost incurred during the year | $ 2,550,000 | $ 3,875,000 | $ 3,250,000 |
Cumulative cost incurred at end of year | $ 2,550,000 | $ 6,425,000 | $ 9,675,000 |
Cumulative cost incurred at end of year | $ 2,550,000 | $ 6,425,000 | $ 9,675,000 |
Add: Estimated costs to complete as of year-end | $ 5,750,000 | $ 3,250,000 | $ 0 |
Total estimated cost | $ 8,300,000 | $ 9,675,000 | $ 9,675,000 |
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) | 30.72289% | 66.40827% | 100.00000% |
Revenue recognized till the date (10000000 * percentage of completion) | $ 3,072,289 | $ 6,640,827 | $ 10,000,000 |
Less: Revenue recognized up to earlier year | $ 0 | $ 3,072,289 | $ 6,640,827 |
Revenue recognized in current year | $ 3,072,289 | $ 3,568,538 | $ 3,359,173 |
Revenue recognized in current year | $ 3,072,289 | $ 3,568,538 | $ 3,359,173 |
Less: cost incurred during the year | $ 2,550,000 | $ 3,875,000 | $ 3,250,000 |
Gross Profit (Loss) | $ 522,289 | $ (306,462) | $ 109,173 |
Your Answer | |||
Year | 2021 | 2022 | 2023 |
Revenue | $ 3,072,289 | $ 3,568,538 | $ 3,359,173 |
Gross Profit (Loss) | $ 522,289 | $ (306,462) | $ 109,173 |
Answer 5
Answer 5 | |||
Year | 2021 | 2022 | 2023 |
Cost incurred during the year | $ 2,550,000 | $ 3,875,000 | $ 4,125,000 |
Cumulative cost incurred at end of year | $ 2,550,000 | $ 6,425,000 | $ 10,550,000 |
Cumulative cost incurred at end of year | $ 2,550,000 | $ 6,425,000 | $ 10,550,000 |
Add: Estimated costs to complete as of year-end | $ 5,750,000 | $ 4,250,000 | $ 0 |
Total estimated cost | $ 8,300,000 | $ 10,675,000 | $ 10,550,000 |
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) | 30.72289% | 60.18735% | 100.00000% |
Revenue recognized till the date (10000000 * percentage of completion) | $ 3,072,289 | $ 6,018,735 | $ 10,000,000 |
Less: Revenue recognized up to earlier year | $ 0 | $ 3,072,289 | $ 6,018,735 |
Revenue recognized in current year | $ 3,072,289 | $ 2,946,446 | $ 3,981,265 |
Revenue recognized in current year | $ 3,072,289 | $ 2,946,446 | $ 3,981,265 |
Less: cost incurred during the year | $ 2,550,000 | $ 3,875,000 | $ 4,125,000 |
Less: Provision For Loss of Project | $ 675,000 | ||
Add: Loss settled from Provision | $ 675,000 | ||
Gross Profit (Loss) | $ 522,289 | $ (1,603,554) | $ 531,265 |
Your Answer | |||
Year | 2021 | 2022 | 2023 |
Revenue | $ 3,072,289 | $ 2,946,446 | $ 3,981,265 |
Gross Profit (Loss) | $ 522,289 | $ (1,603,554) | $ 531,265 |
Hint: | |||
Provision For Loss of Project, When Estimated Project cost is more than Contract Price then Difference between them Provision should be made. And for future Amount of provision should be used for write of loss. For 2022, Provision = estimated cost less Contract revenue = 10,675,000 - 10,000,000 = 675,000 |
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,849, eee Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,072,00 5,328,000 2,160, eee 1,880, eee 2022 $2,738,000 2,590,000 2,650, eee 2,700,eee 5,190, eee 5,420, eee Westgate recognizes revenue over time...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,975,000 $ 3,825,000 $ 1,870,000 Estimated costs to complete as of year-end 5,525,000 1,700,000 0 Billings during the year 2,500,000 4,300,000 3,200,000 Cash collections during the year 2,300,000 4,100,000 3,600,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,550,000 $4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during the year 2,050,000 4,750,000 3,200,000 Cash collections during the year 1,825,000 4,100,000 4,075,000 Westgate recognizes revenue over time according to percentage of...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 4....
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,926,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000 2,660,000 2,860,000 2,800,000 5,060,000 5,360,000 Westgate recognizes revenue over time according to percentage of completion. Problem...