Question


In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000

5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 

2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000 

Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. 

Required: 

  1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years

    2-a. In the journal below, complete the necessary journal entries for the year 2021(credit "Various accounts for construction costs incurred)

    2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts for construction costs incurred).

    2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts for construction costs incurred)

3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. 

4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information 2021 2022 2823 Cost incurred during the year $2,550,000 $3,875,000 $3,250,000 Estimated costs to complete as of a year and 5,75e.ee 3.250.000

5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 

Cost incurred during the year Estimated costs to complete as of year-end 2821 

$2,550,000 5,750,000 2022 $3,875, eee 4,25e,eee 2823 $4,125, eee

2 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Answer 1

Answer 1
Year 2021 2022 2023
Cost incurred during the year $          1,875,000 $          3,375,000 $          2,475,000
Cumulative cost incurred at end of year $          1,875,000 $          5,250,000 $          7,725,000
Cumulative cost incurred at end of year $          1,875,000 $          5,250,000 $          7,725,000
Add: Estimated costs to complete as of year-end $          5,625,000 $          2,250,000 $                           0
Total estimated cost $          7,500,000 $          7,500,000 $          7,725,000
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) 25.00% 70.00% 100.00%
Revenue recognized till the date (10000000 * percentage of completion) $          2,500,000 $          7,000,000 $        10,000,000
Less: Revenue recognized up to earlier year $                           0 $          2,500,000 $          7,000,000
Revenue recognized in current year $          2,500,000 $          4,500,000 $          3,000,000
Revenue recognized in current year $          2,500,000 $          4,500,000 $          3,000,000
Less: cost incurred during the year $          1,875,000 $          3,375,000 $          2,475,000
Gross Profit (Loss) $              625,000 $          1,125,000 $              525,000
Your Answer
Year 2021 2022 2023
Revenue $          2,500,000 $          4,500,000 $          3,000,000
Gross Profit (Loss) $              625,000 $          1,125,000 $              525,000

Answer 2 and 3

? X 2019 10 01.xlsx - Microsoft Excel Sign in INSERT VIEW DEVELOPER FILE HOME PAGE LAYOUT FORMULAS DATA REVIEW L22 F G K M Q? X 2019 10 01.xlsx - Microsoft Excel Sign in INSERT VIEW DEVELOPER FILE НОМE PAGE LAYOUT FORMULAS DATA REVIEW fix L24 X FA L? X 2019 10 01.xlsx - Microsoft Excel Sign in INSERT VIEW DEVELOPER FILE HOME PAGE LAYOUT FORMULAS DATA REVIEW fox N44 FA N F

Answer 4

Answer 4
Year 2021 2022 2023
Cost incurred during the year $          2,550,000 $          3,875,000 $          3,250,000
Cumulative cost incurred at end of year $          2,550,000 $          6,425,000 $          9,675,000
Cumulative cost incurred at end of year $          2,550,000 $          6,425,000 $          9,675,000
Add: Estimated costs to complete as of year-end $          5,750,000 $          3,250,000 $                           0
Total estimated cost $          8,300,000 $          9,675,000 $          9,675,000
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) 30.72289% 66.40827% 100.00000%
Revenue recognized till the date (10000000 * percentage of completion) $          3,072,289 $          6,640,827 $        10,000,000
Less: Revenue recognized up to earlier year $                           0 $          3,072,289 $          6,640,827
Revenue recognized in current year $          3,072,289 $          3,568,538 $          3,359,173
Revenue recognized in current year $          3,072,289 $          3,568,538 $          3,359,173
Less: cost incurred during the year $          2,550,000 $          3,875,000 $          3,250,000
Gross Profit (Loss) $              522,289 $           (306,462) $              109,173
Your Answer
Year 2021 2022 2023
Revenue $          3,072,289 $          3,568,538 $          3,359,173
Gross Profit (Loss) $              522,289 $           (306,462) $              109,173

Answer 5

Answer 5
Year 2021 2022 2023
Cost incurred during the year $          2,550,000 $          3,875,000 $          4,125,000
Cumulative cost incurred at end of year $          2,550,000 $          6,425,000 $        10,550,000
Cumulative cost incurred at end of year $          2,550,000 $          6,425,000 $        10,550,000
Add: Estimated costs to complete as of year-end $          5,750,000 $          4,250,000 $                           0
Total estimated cost $          8,300,000 $        10,675,000 $        10,550,000
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) 30.72289% 60.18735% 100.00000%
Revenue recognized till the date (10000000 * percentage of completion) $          3,072,289 $          6,018,735 $        10,000,000
Less: Revenue recognized up to earlier year $                           0 $          3,072,289 $          6,018,735
Revenue recognized in current year $          3,072,289 $          2,946,446 $          3,981,265
Revenue recognized in current year $          3,072,289 $          2,946,446 $          3,981,265
Less: cost incurred during the year $          2,550,000 $          3,875,000 $          4,125,000
Less: Provision For Loss of Project $              675,000
Add: Loss settled from Provision $              675,000
Gross Profit (Loss) $              522,289 $        (1,603,554) $              531,265
Your Answer
Year 2021 2022 2023
Revenue $          3,072,289 $          2,946,446 $          3,981,265
Gross Profit (Loss) $              522,289 $        (1,603,554) $              531,265
Hint:
Provision For Loss of Project, When Estimated Project cost is more than Contract Price then Difference between them Provision should be made. And for future Amount of provision should be used for write of loss. For 2022, Provision = estimated cost less Contract revenue = 10,675,000 - 10,000,000 = 675,000
Add a comment
Know the answer?
Add Answer to:
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,849, eee Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,072,00 5,328,000 2,160, eee 1,880, eee 2022 $2,738,000 2,590,000 2,650, eee 2,700,eee 5,190, eee 5,420, eee Westgate recognizes revenue over time...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,975,000 $ 3,825,000 $ 1,870,000 Estimated costs to complete as of year-end 5,525,000 1,700,000 0 Billings during the year 2,500,000 4,300,000 3,200,000 Cash collections during the year 2,300,000 4,100,000 3,600,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,550,000 $4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during the year 2,050,000 4,750,000 3,200,000 Cash collections during the year 1,825,000 4,100,000 4,075,000 Westgate recognizes revenue over time according to percentage of...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 4....

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,926,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000 2,080,000 1,840,000 2022 $2,300,000 2,660,000 2,860,000 2,800,000 5,060,000 5,360,000 Westgate recognizes revenue over time according to percentage of completion. Problem...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT