[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to percentage of completion.
2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Westgate Construction Company | ||||
Ans to 1 and 2 | Calculation of Gross Profit | |||
Particulars | 2021 | 2022 | 2023 | |
Contract Price | 10,000,000 | 10,000,000 | 10,000,000 | A |
Cost Incurred during the year | 2,580,000 | 4,042,000 | 2,175,800 | C |
Cost Incurred to date | 2,580,000 | 6,622,000 | 8,797,800 | |
(Cost incurred to date of the present year less Cost incurred to date of the previous year) | ||||
Estimated cost to complete | 6,020,000 | 1,978,000 | - | D |
Estimated total cost | 8,600,000 | 8,600,000 | 8,797,800 | E=C+B |
(Cost Incurred to date+ Estimated cost to complete ) | ||||
Percentage complete | 30.00% | 77.00% | 100.00% | F=B/E |
(Cost Incurred to date/Estimated total cost) | ||||
Revenue to be recognized | 3,000,000 | 4,700,000 | 2,300,000 | G |
(Contract Price*Percentage complete)- revenue previously recognized | ||||
Year 2021: 30% completed. Revenue recognized = 30% x $ 10,000,000 = $ 3,000,000. | ||||
Year 2022: 77% completed. Revenue recognized = 77% x $ 10,000,000 – $ 3,000,000 (previously recognized) = $ 4,700,000. | ||||
Year 2023: 100% completed. Revenue recognized = 100% x $ 10,000,000 – $ 3,000,000- $ 4,770,000 (previously recognized) = $ 2,300,000. | ||||
Gross Profit/(Loss) | 420,000 | 658,000 | 124,200 | H=G-C |
Billings during the year | 2,060,000.00 | 4,562,000.00 | 3,378,000.00 | |
Cash collections during the year | 1,830,000.00 | 4,200,000.00 | 3,970,000.00 |
2021 | 2022 | 2023 | |||||||
Journal Entries | Debit $ | Credit $ | Debit $ | Credit $ | Debit $ | Credit $ | |||
Costs Incurred | CIP (Work-in-progress) | 2,580,000 | 4,042,000 | 2,175,800 | |||||
Cash | 2,580,000 | 4,042,000 | 2,175,800 | ||||||
Billing | Accounts Receivable | 2,060,000 | 4,562,000 | 3,378,000 | |||||
Billing on CIP | 2,060,000 | 4,562,000 | 3,378,000 | ||||||
Receiving Payments | Cash | 1,830,000 | 4,200,000 | 3,970,000 | |||||
Accounts Receivable | 1,830,000 | 4,200,000 | 3,970,000 | ||||||
Period end adjustments for Revenue | Construction Expense | 2,580,000 | 4,042,000 | 2,175,800 | |||||
(Gross Profit entry) | CIP (Work-in-progress) | 420,000 | 658,000 | 124,200 | |||||
Construction Revenue | 3,000,000 | 4,700,000 | 2,300,000 | ||||||
Completing the Project | Billing on CIP | 10,000,000 | |||||||
CIP (Work-in-progress) | 10,000,000 |
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,580,000 6,020,000 2,060,000 1,830,000 2022 $4,042,000 1,978,000 4,562,000 4,200,000 3,378,000 3,970,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,580,000 6,020,000 2,060,000 1,830,000 2022 $4,042,000 1,978,000 4,562,000 4,200,000 3,378,000 3,970,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,580,000 6,020,000 2,060,000 1,830,000 2019 $4,042,000 1,978,000 4,562,000 4,200,000 2020 $2,175,800 0 3,378,000...
he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,580,000 6,020,000 2,060,000 1,830,000 2019 $4,042,000 1,978,000 4,562,000 4,200,000 2020 $2,175,800 0 3,378,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,204,000 5,396,000 2,140,000 1,870,000 2022 $3,192,000 2,204,000 3,256,000 3,200,000 4,604,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...