[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000
Westgate recognizes revenue over time according to percentage of completion.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 2022 2023 Costs incurred during the year $ 2,580,000 $ 3,830,000 $ 3,230,000 Estimated costs to complete as of year-end 6,020,000 3,130,000 0
Particulars | 2021 | 2022 | 2023 | ||
a | Cost incurred | $2,580,000 | $4,042,000 | $2,175,800 | |
b | Cost incurred cumulative | $2,580,000 | $6,622,000 | $8,797,800 | |
c | Estimated completion cost | $6,020,000 | $1,978,000 | $0 | |
d | % of completion | 30.00% | 77.00% | 100% | |
2,580,000/(6,020,000+2,580,000) | 6,622,000/(1,978,000+6,622,000) | ||||
Contract Price = $10,000,000 | |||||
Revenue to be recognised(cumulative) (10,00,000*d) | $3,000,000 | $7,700,000 | $10,000,000 | ||
e | Revenue to recognised per year | $3,000,000 | $4,700,000 | $2,300,000 | |
Gross profit( e - a ) | $420,000 | $658,000 | $124,200 | ||
Cost incurred | $2,580,000 | $3,830,000 | $3,230,000 | ||
Cost incurred cumulative | $2,580,000 | $6,410,000 | $9,640,000 | ||
Estimated completion cost | $6,020,000 | $3,130,000 | $0 | ||
% of completion | 30.00% | 67.19% | 100% | ||
Revenue to be recognised(cumulative) (10,00,000*%) | $3,000,000 | $6,719,078 | $10,000,000 | ||
Revenue per year | $3,000,000 | $3,719,078 | $3,280,922 | ||
Gross profit | $420,000 | -$110,922 | $50,922 | ||
(3000000-2580000) | (3719078-3830000) | (3280922-3230000) |
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,580,000 6,020,000 2,060,000 1,830,000 2022 $4,042,000 1,978,000 4,562,000 4,200,000 3,378,000 3,970,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,580,000 6,020,000 2,060,000 1,830,000 2022 $4,042,000 1,978,000 4,562,000 4,200,000 3,378,000 3,970,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,580,000 6,020,000 2,060,000 1,830,000 2019 $4,042,000 1,978,000 4,562,000 4,200,000 2020 $2,175,800 0 3,378,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,580,000 6,020,000 2,060,000 1,830,000 2019 $4,042,000 1,978,000 4,562,000 4,200,000 2020 $2,175,800 0 3,378,000...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...
The following information applies to the questions displayed below.) In 2021. the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate...
(The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate...