Partial balancesheet | 2018 | 2019 | ||
Current assets | ||||
Accounts recievable | $ 230,000.00 | $ 362,000.00 | ||
Construction in progress | $ 3,000,000.00 | $ 7,700,000.00 | ||
less: billings | $ 2,060,000.00 | $ 6,622,000.00 | ||
$ 940,000.00 | $ 1,078,000.00 | |||
Current liabilities | ||||
Payables | $ 3,000,000.00 | $ 4,562,000.00 |
working note
Degree of completion | 30% | 77% | |
Revenue | =total contract value x percentage completed | ||
$ 3,000,000.00 | $ 7,700,000.00 | ||
less: Costs incurred | $ 2,580,000.00 | $ 6,622,000.00 | |
Profit | $ 420,000.00 | $ 1,078,000.00 | |
Less: profit already recongnized $ 420,000.00 | |||
Profit for year | $ 420,000.00 | $ 658,000.00 |
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,580,000 6,020,000 2,060,000 1,830,000 2019 $4,042,000 1,978,000 4,562,000 4,200,000 2020 $2,175,800 0 3,378,000...
The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,580,000 6,020,000 2,060,000 1,830,000 2022 $4,042,000 1,978,000 4,562,000 4,200,000 3,378,000 3,970,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,580,000 6,020,000 2,060,000 1,830,000 2022 $4,042,000 1,978,000 4,562,000 4,200,000 3,378,000 3,970,000...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...
Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,200,000 Coat incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,400,000 5,600,000 2,000,000 1,800,000 2019 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000...
Required information [The following information applies to the questions displayed below. In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows 2019 $2,542,000 $3,772,000 $2,074,600 1,886,000 2,020,000 4,294,0003,686,000 1,810,000 3,800,000 4,390,000 2018 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 5,658,000 Westgate...