[The following information applies to the questions displayed below.]
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000
Westgate recognizes revenue over time according to percentage of completion.
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 2022 2023
Costs incurred during the year $ 2,580,000 $ 3,830,000 $ 3,990,000 Estimated costs to complete as of year-end 6,020,000 4,160,000 0
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Westgate Construction Company | ||||
Calculation of Gross Profit | ||||
Particulars | 2021 | 2022 | 2023 | |
Contract Price | 10,000,000 | 10,000,000 | 10,000,000 | A |
Cost Incurred during the year | 2,580,000 | 4,042,000 | 2,175,800 | B |
Cost Incurred to date | 2,580,000 | 6,622,000 | 8,797,800 | C |
(Cost incurred to date of the present year less Cost incurred to date of the previous year) | ||||
Estimated cost to complete | 6,020,000 | 1,978,000 | - | D |
Estimated total cost | 8,600,000 | 8,600,000 | 8,797,800 | E=C+D |
(Cost Incurred to date+ Estimated cost to complete ) | ||||
Percentage complete | 30.00% | 77.00% | 100.00% | F=C/E |
(Cost Incurred to date/Estimated total cost) | ||||
Revenue to be recognized | 3,000,000 | 4,700,000 | 2,300,000 | G |
(Contract Price*Percentage complete)- revenue previously recognized | ||||
Year 2021: 30% completed. Revenue recognized = 30% x $ 10,000,000 = $ 3,000,000. | ||||
Year 2022: 77% completed. Revenue recognized = 77% x $ 10,000,000 – $ 3,000,000 (previously recognized) = $ 4,700,000. | ||||
Year 2023: 100% completed. Revenue recognized = 100% x $ 10,000,000 – $ 3,000,000- $ 4,770,000 (previously recognized) = $ 2,300,000. | ||||
Gross Profit/(Loss) | 420,000 | 658,000 | 124,200 | H=G-B |
Billings during the year | 2,060,000.00 | 4,562,000.00 | 3,378,000.00 | |
Cash collections during the year | 1,830,000.00 | 4,200,000.00 | 3,970,000.00 | |
Westgate Construction Company | ||||
Answer 5 | Calculation of Gross Profit | |||
Particulars | 2021 | 2022 | 2023 | |
Contract Price | 10,000,000 | 10,000,000 | 10,000,000 | A |
Cost Incurred during the year | 2,580,000 | 3,830,000 | 3,990,000 | B |
Cost Incurred to date | 2,580,000 | 6,410,000 | 10,400,000 | C |
(Cost incurred to date of the present year less Cost incurred to date of the previous year) | ||||
Estimated cost to complete | 6,020,000 | 1,978,000 | - | D |
Estimated total cost | 8,600,000 | 8,388,000 | 10,400,000 | E=C+D |
(Cost Incurred to date+ Estimated cost to complete ) | ||||
Percentage complete | 30.00% | 76.42% | 100.00% | F=C/E |
(Cost Incurred to date/Estimated total cost) | ||||
Revenue to be recognized | 3,000,000 | 4,641,869 | 2,358,131 | G |
(Contract Price*Percentage complete)- revenue previously recognized | ||||
Year 2021: 30% completed. Revenue recognized = 30% x $ 10,000,000 = $ 3,000,000. | ||||
Year 2022: 76% completed. Revenue recognized = 76% x $ 10,000,000 – $ 3,000,000 (previously recognized) = $ 4,641,869. | ||||
Year 2023: 100% completed. Revenue recognized = 100% x $ 10,000,000 – $ 3,000,000- $ 4,641,869 (previously recognized) = $ 2,3581,131. | ||||
Gross Profit/(Loss) | 420,000 | 811,869 | (1,631,869) | H=G-B |
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,580,000 6,020,000 2,060,000 1,830,000 2022 $4,042,000 1,978,000 4,562,000 4,200,000 3,378,000 3,970,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,580,000 6,020,000 2,060,000 1,830,000 2022 $4,042,000 1,978,000 4,562,000 4,200,000 3,378,000 3,970,000...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,580,000 6,020,000 2,060,000 1,830,000 2019 $4,042,000 1,978,000 4,562,000 4,200,000 2020 $2,175,800 0 3,378,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,580,000 6,020,000 2,060,000 1,830,000 2019 $4,042,000 1,978,000 4,562,000 4,200,000 2020 $2,175,800 0 3,378,000...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,175,800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...
The following information applies to the questions displayed below.) In 2021. the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate...
(The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate...