Question

Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Answer 1
Year 2021 2022 2023
Cost incurred during the year $          2,204,000 $          3,192,000 $          2,424,400
Cumulative cost incurred at end of year $          2,204,000 $          5,396,000 $          7,820,400
Cumulative cost incurred at end of year $          2,204,000 $          5,396,000 $          7,820,400
Add: Estimated costs to complete as of year-end $          5,396,000 $          2,204,000 $                           0
Total estimated cost $          7,600,000 $          7,600,000 $          7,820,400
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) 29.00% 71.00% 100.00%
Revenue recognized till the date (10000000 * percentage of completion) $          2,900,000 $          7,100,000 $        10,000,000
Less: Revenue recognized up to earlier year $                           0 $          2,900,000 $          7,100,000
Revenue recognized in current year $          2,900,000 $          4,200,000 $          2,900,000
Revenue recognized in current year $          2,900,000 $          4,200,000 $          2,900,000
Less: cost incurred during the year $          2,204,000 $          3,192,000 $          2,424,400
Gross Profit (Loss) $              696,000 $          1,008,000 $              475,600
Your Answer
Year 2021 2022 2023
Revenue $          2,900,000 $          4,200,000 $          2,900,000
Gross Profit (Loss) $              696,000 $          1,008,000 $              475,600
Date General Journal Debit Credit
2021 Construction in progress $          2,204,000
Various Accounts $       2,204,000
(To record cost incurred in Progress.)
2021 Accounts receivable $          2,140,000
Billings on construction contract $       2,140,000
(To record Billings to Customer.)
2021 Cash $          1,870,000
Accounts receivable $       1,870,000
(To record cash collected from customer.)
2021 Construction in progress $              696,000
Cost of construction $          2,204,000
Construction Revenue $       2,900,000
(To record recognize Revenue.)
2022 Construction in progress $          3,192,000
Various Accounts $       3,192,000
(To record cost incurred in Progress.)
2022 Accounts receivable $          3,256,000
Billings on construction contract $       3,256,000
(To record Billings to Customer.)
2022 Cash $          3,200,000
Accounts receivable $       3,200,000
(To record cash collected from customer.)
2022 Construction in progress $          1,008,000
Cost of construction $          3,192,000
Construction Revenue $       4,200,000
(To record recognize Revenue.)
2023 Construction in progress $          2,424,400
Various Accounts $       2,424,400
(To record cost incurred in Progress.)
2023 Accounts receivable $          4,604,000
Billings on construction contract $       4,604,000
(To record Billings to Customer.)
2023 Cash $          4,930,000
Accounts receivable $       4,930,000
(To record cash collected from customer.)
2023 Construction in progress $              475,600
Cost of construction $          2,424,400
Construction Revenue $       2,900,000
(To record recognize Revenue.)
2023 Billings on construction contract $        10,000,000
Construction in progress $     10,000,000
(To record completion of contract.)
Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...

    Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...

  • PLEASE HELP WITH ACCTG HW Required information [The following information applies to the questions displayed below.]...

    PLEASE HELP WITH ACCTG HW Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2022 2021 2023 $3,192,000 2,204,000 3,256,000 3,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,204,000 5,396,000...

  • PLEASE HELP WITH ACCTG HW Required information (The following information applies to the questions displayed below.) In...

    PLEASE HELP WITH ACCTG HW Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,204,000 5,396,000 2,140,000 1,870,000 2022...

  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...

  • [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...

  • he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000...

  • The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company...

    The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:     2021 2022 2023 Cost incurred during the year $2,550,000   $4,250,000   $ 1,870,000  Estimated costs to complete as of year-end 5,950,000     1,700,000     0  Billings during the year 2,050,000    4,750,000    3,200,000  Cash collections during the year   1,825,000     4,100,000    4,075,000   Westgate recognizes...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the year 1,870,000 3,200,000 4,930,000 Westgate recognizes revenue over time according to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT