Solution
2021 | 2022 | 2023 | |
Revenue | $ 2,900,000 | $ 4,200,000 | $ 2,900,000 |
Gross profit | $ 696,000 | $ 1,008,000 | $ 475,600 |
Working
Working | 2021 | 2022 | 2023 | |
A | Contract Price | $ 10,000,000 | $ 10,000,000 | $ 10,000,000 |
B | Cost Incurred to Date | $ 2,204,000 | $ 5,396,000 | $ 7,820,400 |
C | Estimated cost yet to be incurred to complete the contract | $ 5,396,000 | $ 2,204,000 | $ 0 |
D = B+C | Total Cost | $ 7,600,000 | $ 7,600,000 | $ 7,820,400 |
E = (D/B) x 100 | % of Completion | 29% | 71% | 100% |
F = A x E | Revenue to date | $ 2,900,000 | $ 7,100,000 | $ 10,000,000 |
G | Revenue of Previous year | $ 0 | $ 2,900,000 | $ 7,100,000 |
H = F - G | Net Revenue this year | $ 2,900,000 | $ 4,200,000 | $ 2,900,000 |
I | Cost to date | $ 2,204,000 | $ 5,396,000 | $ 7,820,400 |
J | Cost to date of previous year | $ 0 | $ 2,204,000 | $ 5,396,000 |
K = I - J | Net Cost for the year | $ 2,204,000 | $ 3,192,000 | $ 2,424,400 |
L = H - K | Gross Profits | $ 696,000 | $ 1,008,000 | $ 475,600 |
PLEASE HELP WITH ACCTG HW Required information (The following information applies to the questions displayed below.) In...
PLEASE HELP WITH ACCTG HW Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2022 2021 2023 $3,192,000 2,204,000 3,256,000 3,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,204,000 5,396,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,204,000 5,396,000 2,140,000 1,870,000 2022 $3,192,000 2,204,000 3,256,000 3,200,000 4,604,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the year 1,870,000 3,200,000 4,930,000 Westgate recognizes revenue over time according to...
! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...