The following information applies to the questions displayed
below .]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows: 2021 2022 2023 Cost incurred
during the year $2,550,000 $4,250,000 $
1,870,000 Estimated costs to complete as of year-end
5,950,000 1,700,000
0 Billings during the year
2,050,000 4,750,000
3,200,000 Cash collections during the
year 1,825,000 4,100,000
4,075,000
Westgate recognizes revenue over time according to percentage of completion
2-a. In the journal below, complete the necessary journal
entries for the year 2021 (credit "Various accounts" for
construction costs incurred). 2-b. In the journal below, complete
the necessary journal entries for the year 2022 (credit "Various
accounts" for construction costs incurred). 2-c. In the journal
below, complete the necessary journal entries for the year 2023
(credit "Various accounts" for construction costs incurred).
Complete this question by entering your answers in the tabs
below.
In the journal below, complete the necessary journal entries for
the year 2021 (credit "Various accounts" for construction costs
incurred). (If no entry is required for a transaction/event, select
"No journal entry required" in the first account field.)
Req 2A Req 2B Req 2C For all three years
Record construction costs.
Record progress billings.
Record cash collections.
Record gross profit (loss).
all of the requirements thank you
Part 2A
Date |
general journal |
debit |
credit |
2021 |
construction in progress |
2550000 |
|
Various accounts |
2550000 |
||
2021 |
accounts receivable |
2050000 |
|
Bills on construction contract |
2050000 |
||
2021 |
cash |
1825000 |
|
Accounts receivable |
1825000 |
||
2021 |
construction in progress |
450000 |
|
Cost of construction |
2550000 |
||
Revenue from long-term contracts |
3000000 |
Revenue = (2550000/(2550000+5950000))*10000000 = 3000000
Part 2 B
Date |
general journal |
debit |
credit |
2022 |
construction in progress |
4250000 |
|
Various accounts |
4250000 |
||
2022 |
accounts receivable |
4750000 |
|
Bills on construction contract |
4750000 |
||
2022 |
cash |
4100000 |
|
Accounts receivable |
4100000 |
||
2022 |
construction in progress |
750000 |
|
Cost of construction |
4250000 |
||
Revenue from long-term contract |
5000000 |
Revenue = ((2550000+4250000)/( 2550000+4250000+1700000))*10000000 = 8000000-3000000 = 5000000
Part 2 C
Date |
general journal |
debit |
credit |
2023 |
construction in progress |
1870000 |
|
Various accounts |
1870000 |
||
2023 |
Accounts receivable |
3200000 |
|
Bills on construction contract |
3200000 |
||
2023 |
Cash |
4075000 |
|
Accounts receivable |
4075000 |
||
2023 |
Construction in progress |
130000 |
|
Cost of construction |
1870000 |
||
Revenue from long-term contract |
2000000 |
Revenue = 10000000-3000000-5000000 = 2000000
The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company...
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
he following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,204,000 5,396,000 2,140,000 1,870,000 2022 $3,192,000 2,204,000 3,256,000 3,200,000 4,604,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 2023 $2,259,400 0 4,154,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000...
The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for 10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 2019 2,542,000 $3,772,000 $2,074,600 1,886,000 2,020,000 4,294,000 3,686,000 1,810,000 3,800,000 4,390,000 2018 Cost incurred during the year Estimated costs to complete as of year-end Billinga during the year Cash collections during the year 5, 658,000 Westgate...
Required information The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,400,000 5,600,000 2,000,000 1,800,000 2019 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,550,000 $4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during the year 2,050,000 4,750,000 3,200,000 Cash collections during the year 1,825,000 4,100,000 4,075,000 Westgate recognizes revenue over time according to percentage of...