Question

Required information The following information applies to the questions displayed below.) In 2018, the Westgate Construction
0 0
Add a comment Improve this question Transcribed image text
Answer #1

POCM Computation

Latest forecast Actuals
Particulars Contract Value Total Budgeted Cost Budgeted Profit (Loss) Budgeted Profit (Loss) % Cost incurred upto Reporting Date Stage of Completion (%) Revenue Recognition Profit (Loss) Profit (Loss) % Expected loss Total Profit (Loss) Progress Billings
(Certified Amount)
WIP
YTD- Dec'20     10,000,000             8,200,000    1,800,000 18.00% 8,200,000              100.00             10,000,000               1,800,000 18.00%                          -                1,800,000         10,000,000                     -  
YTD- Dec'19     10,000,000             8,000,000    2,000,000 20.00%                  6,000,000                75.00               7,500,000               1,500,000 20.00%                          -                1,500,000           6,000,000          1,500,000
YTD- Dec'18     10,000,000             8,000,000    2,000,000 20.00%    2,400,000 30.00 3,000,000    600,000 20.00%                   -      600,000 2,000,000          1,000,000

Journal Entries to be passed for westgate construction company for the year 2018

(I) Construction in progress A/c 2,400,000

To Cash 2,400,000

(Being amount paid for construction)

(II) Accounts receivable A/c Dr. 2,000,000

   To Billings on construction contract 2,000,000

(being amount billed to customer)

(III) Cash A/c Dr. 1,800,000

   To Accounts receivable A/c 1,800,000

(being cash collected from accounts receivable)

(IV) Construction in progress A/c 1,000,000

Construction expense A/c 2,000,000

To Construction revenue A/c 3,000,000

(being revenue recognised for the year)

Journal Entries to be passed for westgate construction company for the year 2019

(I) Construction in progress A/c 3,600,000

To Cash 3,600,000

(Being amount paid for construction)

(II) Accounts receivable A/c Dr. 4,000,000

   To Billings on construction contract 4,000,000

(being amount billed to customer)

(III) Cash A/c Dr. 3,600,000

   To Accounts receivable A/c 3,600,000

(being cash collected from accounts receivable)

(IV) Construction in progress A/c 800,000

Construction expense A/c 3,800,000

To Construction revenue A/c 4,500,000

(being revenue recognised for the year)

Journal Entries to be passed for westgate construction company for the year 2020

(I) Construction in progress A/c 2,200,000

To Cash 2,200,000

(Being amount paid for construction)

(II) Accounts receivable A/c Dr. 4,000,000

   To Billings on construction contract 4,000,000

(being amount billed to customer)

(III) Cash A/c Dr. 4,600,000

   To Accounts receivable A/c 4,600,000

(being cash collected from accounts receivable)

(IV) Construction expense A/c 2,500,000

To Construction revenue A/c 2,500,000

(being revenue recognised for the year)

(V) Billing on construction contract A/c 10,000,000

   To Construction in progress 10,000,000

(being contra account set off)

Add a comment
Know the answer?
Add Answer to:
Required information The following information applies to the questions displayed below.) In 2018, the Westgate Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000...

  • Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000...

  • The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered...

    The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for 10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 2019 2,542,000 $3,772,000 $2,074,600 1,886,000 2,020,000 4,294,000 3,686,000 1,810,000 3,800,000 4,390,000 2018 Cost incurred during the year Estimated costs to complete as of year-end Billinga during the year Cash collections during the year 5, 658,000 Westgate...

  • MHE Reader construction in progress balance sheet connect - Google Search In 2018, The Westgate Con...

    MHE Reader construction in progress balance sheet connect - Google Search In 2018, The Westgate Con Saved Help Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash...

  • Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction...

    Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,200,000 Coat incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,400,000 5,600,000 2,000,000 1,800,000 2019 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000...

  • Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...

    Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...

  • The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company...

    The following information applies to the questions displayed below .] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:     2021 2022 2023 Cost incurred during the year $2,550,000   $4,250,000   $ 1,870,000  Estimated costs to complete as of year-end 5,950,000     1,700,000     0  Billings during the year 2,050,000    4,750,000    3,200,000  Cash collections during the year   1,825,000     4,100,000    4,075,000   Westgate recognizes...

  • Requlred Informatlon The following information applies to the questions displayed below. In 2018,...

    Requlred Informatlon The following information applies to the questions displayed below. In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2819 $2,284,8e $3,192,80 $2,424,488 2818 2828 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 5, 396, 8e 2,284,88e 2,148,88e 3,256,888 4,684,888 1,878,83...

  • Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction...

    Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,400,000 5,600,000 2,000,000 1,800,000 2019 $3,600,000 2.000.000 4,000,000 3,600,000 4.000.000 4.600.000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT