2021 | 2022 | 2023 | |
Contract Price (a) | 10000000 | 10000000 | 10000000 |
Less: Estimated Cost | |||
Costs incurred to date | 2016000 | 4824000 | 7437600 |
Estimated costs to complete | 5184000 | 2376000 | 0 |
Estimated total costs (b) | 7200000 | 7200000 | 7437600 |
Estimated gross profit (a-b) | 2800000 | 2800000 | 2562400 |
% of completion | 28.00% | 67.00% | 100.00% |
(Cost incurred till date / Total costs) | |||
Gross profit earned | 784000 | 1876000 | 2562400 |
Less: Gross profit earned in previous year | 0 | 784000 | 784000 |
Gross profit recognised | 784000 | 1092000 | 1778400 |
Construction Revenue | 2800000 | 6700000 | 10000000 |
Construction Revenue to be recognised over time | 2800000 | 6700000 | 7200000 |
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Help The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 5,176,000 5,610,000 Westgate...
Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 2023 $ 2,613,600 0...
Help In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 0 5,176,000 5,610,000 Westgate recognizes revenue over time according to percentage of...
Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000...