Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the year 1,890,000 2,500,000 5,610,000 Westgate recognizes revenue over time according to percentage of completion.
Solution:
Balance sheet | 2021 | 2022 | ||
Current assets: | ||||
Accounts receivable | $290,000 | $434,000 | ||
Construction in progress | $2,800,000 | $6,700,000 | ||
Less: Billings | ($2,180,000) | ($4,824,000) ($21,80,000+$2,644,000) | ||
Costs and profit in excess of billings | $620,000 | $1,876,000 | ||
Current liabilities: | ||||
Billings in excess of costs | $164,000 | $0 |
Working:
Account receivable:
2021 = $2,180,000 -$1,890,000
=$290,000
2022 = $290,000+($2,644,000 -$2,500,000)
=$434,000
Calculation of percent of completion:
2021 | 2022 | |
Cumulative costs to date | $2,016,000 | $4,824,000 ($2,106,000+$2,808,000) |
Add: Estimate costs to complete as of year end | $5,184,000 | $2,376,000 |
Estimated total cost | $7,200,000 | $7,200,000 |
Percent of completion | 28% ($2,106,000/$7,200,000) |
67% ($4,824,000/$7,200,000) |
calculation of constructed value :
2021 =$10,000,000*28%
=$2,800,000
2022 =$10,000,000*67%
=$6,700,000
Calculation of billing in excess costs :
2021 =$2,180,000 -$2,016,000
=$164,000
2022 =$164,000 +($2,644,000 -$2,808,000)
=$0
Please give a Thumbs up ?. Thanks!!
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Required information [The following information applies to the
questions displayed below.] In 2021, the Westgate Construction
Company entered into a contract to construct a road for Santa Clara
County for $10,000,000. The road was completed in 2023. Information
related to the contract is as follows: 2021 2022 2023 Cost incurred
during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs
to complete as of year-end 5,184,000 2,376,000 0 Billings during
the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information [The following information applies to the
questions displayed below.] In 2021, the Westgate Construction
Company entered into a contract to construct a road for Santa Clara
County for $10,000,000. The road was completed in 2023. Information
related to the contract is as follows: 2021 2022 2023 Cost incurred
during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs
to complete as of year-end 5,184,000 2,376,000 0 Billings during
the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 2023 $2,613,600 0 5,176,000...
Help The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 5,176,000 5,610,000 Westgate...
Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 2023 $ 2,613,600 0...
Help In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 0 5,176,000 5,610,000 Westgate recognizes revenue over time according to percentage of...
Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000...