Question

Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the year 1,890,000 2,500,000 5,610,000 Westgate recognizes revenue over time according to percentage of completion.

Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Balance sheet 2021 2022
Current assets:
Accounts receivable $290,000 $434,000
Construction in progress $2,800,000 $6,700,000
Less: Billings ($2,180,000) ($4,824,000) ($21,80,000+$2,644,000)
Costs and profit in excess of billings $620,000 $1,876,000
Current liabilities:
Billings in excess of costs $164,000 $0

Working:

Account receivable:

2021 = $2,180,000 -$1,890,000

=$290,000

2022 = $290,000+($2,644,000 -$2,500,000)

=$434,000

Calculation of percent of completion:

2021 2022
Cumulative costs to date $2,016,000 $4,824,000 ($2,106,000+$2,808,000)
Add: Estimate costs to complete as of year end $5,184,000 $2,376,000
Estimated total cost $7,200,000 $7,200,000
Percent of completion 28% ($2,106,000/$7,200,000)

67% ($4,824,000/$7,200,000)

calculation of constructed value :

2021 =$10,000,000*28%

=$2,800,000

2022 =$10,000,000*67%

=$6,700,000

Calculation of billing in excess costs :

2021 =$2,180,000 -$2,016,000

=$164,000

2022 =$164,000 +($2,644,000 -$2,808,000)

=$0

Please give a Thumbs up ?. Thanks!!

Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 2023 $2,613,600 0 5,176,000...

  • Help The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company...

    Help The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 5,176,000 5,610,000 Westgate...

  • Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 2023 $ 2,613,600 0...

  • Help In 2021, the Westgate Construction Company entered into a contract to construct a road for...

    Help In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,613,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 0 5,176,000 5,610,000 Westgate recognizes revenue over time according to percentage of...

  • Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...

  • Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...

  • The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered...

    The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...

  • ! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate...

    ! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT