3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8.210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705.000. 2022 billings were $2.820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,450,000. During 2018, costs of $2,180,000 were incurred, with estimated costs of $4,180,000 yet to be incurred. Billings of $2,716,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,716,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,966,000, and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of $3,900,000...