On February 1, 2018, Arrow Construction Company entered into a
three-year construction contract to build a bridge for a price of
$8,420,000. During 2018, costs of $2,140,000 were incurred with
estimated costs of $4,140,000 yet to be incurred. Billings of
$2,640,000 were sent, and cash collected was $2,390,000.
In 2019, costs incurred were $2,640,000 with remaining costs
estimated to be $3,810,000. 2019 billings were $2,890,000 and
$2,615,000 cash was collected. The project was completed in 2020
after additional costs of $3,940,000 were incurred. The company’s
fiscal year-end is December 31. Arrow recognizes revenue over time
according to the percentage of completion.
Required:
1. Compute the amount of revenue and gross profit
or loss to be recognized in 2018, 2019, and 2020 using the
percentage of completion method?
2a. Prepare journal entries for 2018 to record the
transactions described (credit "various accounts" for construction
costs incurred).
2b. Prepare journal entries for 2019 to record the
transactions described (credit "various accounts" for construction
costs incurred).
3a. Prepare a partial balance sheet to show the
presentation of the project as of December 31, 2018.
3b. Prepare a partial balance sheet to show the
presentation of the project as of December 31, 2019.
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimat...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,350,000. During 2021, costs of $2,140,000 were incurred, with estimated costs of $4,140,000 yet to be incurred. Billings of $2,668,000 were sent, and cash collected was $2,390,000. In 2022, costs incurred were $2,668,000 with remaining costs estimated to be $3,810,000. 2022 billings were $2,918,000, and $2,615,000 cash was collected. The project was completed in 2023 after additional costs of...
3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2019, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2019 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2020 after additional costs...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,450,000. During 2018, costs of $2,180,000 were incurred, with estimated costs of $4,180,000 yet to be incurred. Billings of $2,716,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,716,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,966,000, and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,330,000. During 2021, costs of $2,110,000 were incurred with estimated costs of $4,110,000 yet to be incurred. Billings of $2,610,000 were sent, and cash collected was $2,360,000. In 2022, costs incurred were $2,610,000 with remaining costs estimated to be $3,765,000. 2022 billings were $2,860,000 and $2,585,000 cash was collected. The project was completed in 2023 after additional costs of $3,910,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of $3,900,000...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...