Question

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimat...

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000.

In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of $3,940,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to the percentage of completion.

Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2018, 2019, and 2020 using the percentage of completion method?
2a. Prepare journal entries for 2018 to record the transactions described (credit "various accounts" for construction costs incurred).
2b. Prepare journal entries for 2019 to record the transactions described (credit "various accounts" for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019.

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Requirement-1 2018 2019 2020 $2,640,000 $2,890,000 $2,890,000 [2020 $8,420,000 $2640000- $2890000] Billings during the year 2Requirement-2: Requirement-2fa Requirement-2(c Requirement-2(b) Account Titles 2018 2019 2020 Debit Debit Credit Credit DebitRequirement-3 Requirement-3(a) Requirement-3(b) Balance Sheet (Partial) 2018 2019 Current Assets $525,000 [2018 $2640000-$239

Add a comment
Know the answer?
Add Answer to:
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimat...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT