Answer 1 | |||
Gross profit recognize under completed contract method when Company completed contract. | |||
Provision For Loss of Project, When Estimated Project cost is more than Contract Price then Difference between them Provision should be made. And for future Amount of provision should be used for write of loss. | |||
2018 | 2019 | 2020 | |
Cost incurred during the year | $ 2,000,000 | $ 2,500,000 | $ 3,800,000 |
Cumulative cost incurred at end of year | $ 2,000,000 | $ 4,500,000 | $ 8,300,000 |
Cumulative cost incurred at end of year | $ 2,000,000 | $ 4,500,000 | $ 8,300,000 |
Add: Estimated costs to complete as of year-end | $ 4,000,000 | $ 3,600,000 | $ 0 |
Total estimated cost | $ 6,000,000 | $ 8,100,000 | $ 8,300,000 |
Less: Contract value | $ 8,000,000 | $ 8,000,000 | $ 8,000,000 |
Loss (If any) | $ 100,000 | $ 300,000 | |
Less: Loss settled from Provision | $ (100,000) | ||
Gross Loss | $ - | $ 100,000 | $ 200,000 |
Revenue Recognized = Cost incurred plus Gross Profit Less Gross Loss (if any) | |||
Cost incurred during the year | $ 2,000,000 | $ 2,500,000 | $ 3,800,000 |
Less: Gross Loss | $ - | $ 100,000 | $ 200,000 |
Revenue | $ 2,000,000 | $ 2,400,000 | $ 3,600,000 |
Answer 2 | |||
Date | General Journal | Debit | Credit |
2018 | Construction in progress | $ 2,000,000 | |
Various Accounts | $ 2,000,000 | ||
(To record cost incurred in Progress.) | |||
2018 | Accounts receivable | $ 2,500,000 | |
Billings on construction contract | $ 2,500,000 | ||
(To record Billings to Customer.) | |||
2018 | Cash | $ 2,250,000 | |
Accounts receivable | $ 2,250,000 | ||
(To record cash collected from customer.) | |||
2018 | Cost of construction | $ 2,000,000 | |
Construction Revenue | $ 2,000,000 | ||
(To record recognize Revenue.) | |||
2019 | Construction in progress | $ 2,500,000 | |
Various Accounts | $ 2,500,000 | ||
(To record cost incurred in Progress.) | |||
2019 | Accounts receivable | $ 2,750,000 | |
Billings on construction contract | $ 2,750,000 | ||
(To record Billings to Customer.) | |||
2019 | Cash | $ 2,475,000 | |
Accounts receivable | $ 2,475,000 | ||
(To record cash collected from customer.) | |||
2019 | Cost of construction | $ 2,500,000 | |
Construction in progress | $ 100,000 | ||
Construction Revenue | $ 2,400,000 | ||
(To record recognize Revenue.) |
Answer 3 | ||||
Partial balance sheet | ||||
2018 | 2019 | |||
Current assets | ||||
Accounts receivable | $ 250,000 | $ 525,000 | ||
Current liability | ||||
Billings | $ 2,500,000 | $ 5,250,000 | ||
Less: Construction in progress | $ 2,000,000 | $ 4,400,000 | ||
Billings in excess of Cost | $ 500,000 | $ 850,000 |
Year | 2018 | 2019 |
Accounts receivable at beginning | $ - | $ 250,000 |
Add: Amount billed | $ 2,500,000 | $ 2,750,000 |
Less: Cash received | $ 2,250,000 | $ 2,475,000 |
Accounts receivable at Ending | $ 250,000 | $ 525,000 |
Beginning Construction in progress | $ - | $ 2,000,000 |
Add: Cost incurred | $ 2,000,000 | $ 2,500,000 |
Add: Gross profit (loss) | $ 0 | $ (100,000) |
Ending Construction in progress | $ 2,000,000 | $ 4,400,000 |
Billing Amount | $ 2,500,000 | $ 2,750,000 |
Cumulative Billing amount | $ 2,500,000 | $ 5,250,000 |
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,450,000. During 2018, costs of $2,180,000 were incurred, with estimated costs of $4,180,000 yet to be incurred. Billings of $2,716,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,716,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,966,000, and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,060,000 were incurred, with estimated costs of $4,060,000 yet to be incurred. Billings of $2,572,000 were sent, and cash collected was $2,310,000. In 2022, costs incurred were $2,572,000 with remaining costs estimated to be $3,690,000. 2022 billings were $2,822,000, and $2,535,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2021, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000. In 2022, costs incurred were $2,692,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,942,000, and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...