Question

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Answer 1
Gross profit recognize under completed contract method when Company completed contract.
Provision For Loss of Project, When Estimated Project cost is more than Contract Price then Difference between them Provision should be made. And for future Amount of provision should be used for write of loss.
2018 2019 2020
Cost incurred during the year $        2,000,000 $           2,500,000 $       3,800,000
Cumulative cost incurred at end of year $        2,000,000 $           4,500,000 $       8,300,000
Cumulative cost incurred at end of year $        2,000,000 $           4,500,000 $       8,300,000
Add: Estimated costs to complete as of year-end $        4,000,000 $           3,600,000 $                        0
Total estimated cost $        6,000,000 $           8,100,000 $       8,300,000
Less: Contract value $        8,000,000 $           8,000,000 $       8,000,000
Loss (If any) $              100,000 $           300,000
Less: Loss settled from Provision $         (100,000)
Gross Loss $                       -   $              100,000 $           200,000
Revenue Recognized = Cost incurred plus Gross Profit Less Gross Loss (if any)
Cost incurred during the year $        2,000,000 $           2,500,000 $       3,800,000
Less: Gross Loss $                       -   $              100,000 $           200,000
Revenue $        2,000,000 $           2,400,000 $       3,600,000
Answer 2
Date General Journal Debit Credit
2018 Construction in progress $        2,000,000
Various Accounts $           2,000,000
(To record cost incurred in Progress.)
2018 Accounts receivable $        2,500,000
Billings on construction contract $           2,500,000
(To record Billings to Customer.)
2018 Cash $        2,250,000
Accounts receivable $           2,250,000
(To record cash collected from customer.)
2018 Cost of construction $        2,000,000
Construction Revenue $           2,000,000
(To record recognize Revenue.)
2019 Construction in progress $        2,500,000
Various Accounts $           2,500,000
(To record cost incurred in Progress.)
2019 Accounts receivable $        2,750,000
Billings on construction contract $           2,750,000
(To record Billings to Customer.)
2019 Cash $        2,475,000
Accounts receivable $           2,475,000
(To record cash collected from customer.)
2019 Cost of construction $        2,500,000
Construction in progress $              100,000
Construction Revenue $           2,400,000
(To record recognize Revenue.)
Answer 3
Partial balance sheet
2018 2019
Current assets
Accounts receivable $            250,000 $           525,000
Current liability
Billings $                                                                                                2,500,000 $           5,250,000
Less: Construction in progress $                                                                                                2,000,000 $           4,400,000
Billings in excess of Cost $            500,000 $           850,000
Year 2018 2019
Accounts receivable at beginning $                       -   $              250,000
Add: Amount billed $        2,500,000 $           2,750,000
Less: Cash received $        2,250,000 $           2,475,000
Accounts receivable at Ending $            250,000 $              525,000
Beginning Construction in progress $                       -   $           2,000,000
Add: Cost incurred $        2,000,000 $           2,500,000
Add: Gross profit (loss) $                         0 $            (100,000)
Ending Construction in progress $        2,000,000 $           4,400,000
Billing Amount $        2,500,000 $           2,750,000
Cumulative Billing amount $        2,500,000 $           5,250,000
Add a comment
Know the answer?
Add Answer to:
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,450,000. During 2018, costs of $2,180,000 were incurred, with estimated costs of $4,180,000 yet to be incurred. Billings of $2,716,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,716,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,966,000, and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimat...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,060,000 were incurred, with estimated costs of $4,060,000 yet to be incurred. Billings of $2,572,000 were sent, and cash collected was $2,310,000. In 2022, costs incurred were $2,572,000 with remaining costs estimated to be $3,690,000. 2022 billings were $2,822,000, and $2,535,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2021, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000. In 2022, costs incurred were $2,692,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,942,000, and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT