Question

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000.

In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of $3,820,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.

Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2018, 2019, and 2020 using the percentage of completion method?
2a. Prepare journal entries for 2018 to record the transactions described (credit "various accounts" for construction costs incurred).
2b. Prepare journal entries for 2019 to record the transactions described (credit "various accounts" for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019.

Please explain the 2019 construction expense. I am adding the cost incurred in 2018 of 2,020,000 and the cost incurred in 2019 of $2,520,000.

Compute the amount of revenue and gross profit or loss to be recognized in 2018, 2019, and 2020 using the percentage of compl

Recognized in 2019 2019 Recognized in prior To date years 4,478,878 2,695,562 4,540,000 X $ 2,020,000 675,562 Construction re

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
Ques 1
2016 2017 2018
Estimated total gross profit(loss) $                   2,020,000 $                               (110,000)
Actual total gross profit(loss) $                       (300,000)
Numerator / Denominator = %completion
Actual costs to date / Estimated total costs =
2016 2020000 / 6040000 = 33.4437%
2017 4540000 / 8170000 = 55.5692%
2018 / = 100.0000%
2016
to date Recognised in prior years Recognised in 2016
Construction revenue $                   2,695,563 $                     2,695,563
Construction expense $                   2,020,000 $                     2,020,000
Gross Profit (loss) $                      675,563 $                         675,563
2017
to date Recognised in prior years Recognised in 2016
Construction revenue $                   4,478,874 $                             2,695,563 $                     1,783,311
Construction expense $                   4,588,874 $                             2,020,000 $                     2,568,874
Gross Profit (loss) $                     (110,000) $                                675,563 $                       (785,563)
2018
to date Recognised in prior years Recognised in 2016
Construction revenue $                   8,060,000 $                             4,478,874 $                     3,581,126
Construction expense $                   8,360,000 $                             4,588,874 $                     3,771,126
Gross Profit (loss) $                     (300,000) $                               (110,000) $                       (190,000)
Ques 2a
Year Accounts debit credit
2016 Constuction in progress $         2,020,000
Various accounts $         2,020,000
2016 Accounts receivable $         2,520,000
Billings on construction contract $         2,520,000
2016 Cash $         2,270,000
Accounts receivable $         2,270,000
2016 Construction in progress $            675,563
Cost of construction $         2,020,000
Revenue from long term contracts $         2,695,563
2016 No entry
Year Accounts debit credit
2017 Constuction in progress $         2,520,000
Various accounts $         2,520,000
2017 Accounts receivable $         2,770,000
Billings on construction contract $         2,770,000
2017 Cash $         2,495,000
Accounts receivable $         2,495,000
2017 No entry
2017 Cost of construction $         2,568,874
Construction in progress $            785,563
Revenue from long term contracts $         1,783,311
Ques 3a
Balance sheet-2016
Current Assets
Accounts receivable $         250,000 2520000-2270000
Cost and profit in excess of billings $         175,563 2020000+675563-2520000
Current liabilities
Balance sheet-2017
Current Assets
Accounts receivable $         525,000 2770000+250000-2495000
Cost and profit in excess of billings
Current liabilities
Billings in excess of billings $         860,000 2520000+2770000-2020000-2520000--110000
Add a comment
Know the answer?
Add Answer to:
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • I am lost. This all that I have so far...... On February 1, 2018, Arrow Construction...

    I am lost. This all that I have so far...... On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected....

  • it says it's incomplete, please help On February 1, 2018, Arrow Construction Company entered into a...

    it says it's incomplete, please help On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,600,000. During 2018, costs of $2,200,000 were incurred with estimated costs of $4,200,000 yet to be incurred. Billings of $2,700,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,700,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,950,000 and $2,675,000 cash was collected. The project was completed...

  • 3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred...

    3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2019, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2019 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2020 after additional costs...

  • On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2.475,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimat...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,450,000. During 2018, costs of $2,180,000 were incurred, with estimated costs of $4,180,000 yet to be incurred. Billings of $2,716,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,716,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,966,000, and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT