Year | Cost Incurred | Further Cost Estimated | Total Cost | % of completion | Amount Received till date | Amount of Revenue | Provision for Loss |
2021 | $ 20,00,000.00 | $ 40,00,000.00 | $ 60,00,000.00 | 33.33333333 | $ 22,50,000.00 | $ 26,66,666.67 | $ - |
2022 | $ 45,00,000.00 | $ 36,00,000.00 | $ 81,00,000.00 | 55.55555556 | $ 47,25,000.00 | $ 44,44,444.44 | $ 1,00,000.00 |
2023 | $ 83,00,000.00 | $ - | $ 83,00,000.00 | 100 | $ 32,75,000.00 | $ 80,00,000.00 |
2021 | |||
To date | Recognized Prior | Recognized in 2021 | |
Construction Revenue | $ 26,66,666.67 | $ - | $ 26,66,666.67 |
Construction Expense | $ 20,00,000.00 | $ - | $ 20,00,000.00 |
Gross Profit /loss | $ 6,66,666.67 | $ - | $ 6,66,666.67 |
2022 | |||
To date | Recognized Prior | Recognized in 2022 | |
Construction Revenue | $ 44,44,444.44 | $ 26,66,666.67 | $ 17,77,777.78 |
Construction Expense | $ 45,00,000.00 | $ 20,00,000.00 | $ 25,00,000.00 |
Gross Profit /loss | $ -55,555.56 | $ 6,66,666.67 | $ -7,22,222.22 |
2023 | |||
To date | Recognized Prior | Recognized in 2023 | |
Construction Revenue | $ 80,00,000.00 | $ 44,44,444.44 | $ 35,55,555.56 |
Construction Expense | $ 83,00,000.00 | $ 45,00,000.00 | $ 38,00,000.00 |
Gross Profit /loss | $ -3,00,000.00 | $ -55,555.56 | $ -2,44,444.44 |
2A)
Journal Entries in the year 2021
No loss need to recognized Immediately as the Cost expected is with in the invoice value
Invoice value (-) Total Cost = $80,00,000 - $ 60,00,000= profit $20,00,000
Year 2021 | ||||
Construction In Progress | Dr | 20,00,000.00 | ||
To Cash A/c | $ 20,00,000.00 | |||
( Being Amount of the Expenses Incurred for the construction) | ||||
Accounts receivable | Dr | $ 26,66,666.67 | ||
To Billings on construction contract | $ 26,66,666.67 | |||
( being the amount of receivable on % completion basis to be received) | ||||
Cash | Dr | 22,50,000.00 | ||
To Accounts receivable | $ 22,50,000.00 | |||
( being the amount of received During The year) | ||||
Billings on construction contract A/c | Dr | $ 26,66,666.67 | ||
To Contract Revenue | $ 26,66,666.67 | |||
( being the amount of Revenue Transfer th construction A/c) | ||||
Contract Revenue A/c | Dr | $ 26,66,666.67 | ||
To Construction In Progress | $ 20,00,000.00 | |||
To Gross Profit | $ 6,66,666.67 | |||
( being Gross Profit Recognized) |
On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...
please complete it in this format. On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8.210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705.000. 2022 billings were $2.820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...