Question

Riverbed Construction Company uses the percentage-of-completion method of accounting. In 2017, Riverbed began work under contract...

Riverbed Construction Company uses the percentage-of-completion method of accounting. In 2017, Riverbed began work under contract #E2-D2, which provided for a contract price of $2,195,000. Other details follow:

2017

2018

Costs incurred during the year $695,310 $1,404,000
Estimated costs to complete, as of December 31 921,690 –0–
Billings to date 426,000 2,195,000
Collections during the year 352,000 1,475,000

Collapse question part

What portion of the total contract price would be recognized as revenue in 2017? In 2018?
Revenue recognized in 2017 $
Revenue recognized in 2018
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Explanation:

2107 2018
Contract peice $2,195,000 $2,195,000
Percentage of completion 43% 100%
Realized Revenue $943,850 $2,195,000
Less: Realized revenue from last year - ($943,850)
Realized recognized for the year $943,850 $1,252,250

Percentage of completion for 2017 =$695,310/$1,617,000 =43%

_____×____

All the best

Add a comment
Know the answer?
Add Answer to:
Riverbed Construction Company uses the percentage-of-completion method of accounting. In 2017, Riverbed began work under contract...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 18-36 Marin Construction Company uses the percentage of completion method of accounting in 2017, Marin...

    Exercise 18-36 Marin Construction Company uses the percentage of completion method of accounting in 2017, Marin began work under contract E2-02, which provided for a contract price of 52,195,000. Other details follow 2017 2018 Costs incurred during the year 5695,310 $1,404,000 Estimated costs to complete, as of December 31921,690 0 Billings to date 426,000 2,195,000 Collections during the year 352,000 1,475,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in...

  • Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work...

    Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 -0- Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017...

  • Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract...

    Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract #E2-D2, which provided for a contract price of $2,227,000. Other details follow: 2017 2018 Cost incurred during the year $660240 $1422000 Estimated costs to complete, as of December 31 911760 0 Billings to date 425000 2227000 Collections during the year 347000 1523000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $______________ Revenue...

  • Hamilton Construction Company uses the percentage-of-completion method of accounting. In 2020, Hamilton began work on the...

    Hamilton Construction Company uses the percentage-of-completion method of accounting. In 2020, Hamilton began work on the construction of a hospital, which provides for a contract price of $2,195,000. Other details follow: 20XO 20X1 Costs incurred during the year 637,600 1,000,000 Total estimated cost 1,594,000 1,637,600 Billings during the year 427,000 2,195,000 Collections during the year 343,000 1,509,000 What portion of the total contract price would be recognized as revenue in 20x0? 2,195,000 878,000 1,097,500 427,000 343,000

  • During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ 258,000 Gross...

  • During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job...

    During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...

  • CALCULATOR PRINTER VERSION BACK Problem 18-10 On March 1, 2017, Riverbed Construction Company contracted to construct...

    CALCULATOR PRINTER VERSION BACK Problem 18-10 On March 1, 2017, Riverbed Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,490,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,907,000 $2,465,800 $1,987,200 Estimated costs to complete the contract...

  • During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...

  • During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was complete...

    During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...

  • 2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes...

    2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2018 (from construction progress billings) $ 37.5 Actual construction costs incurred in 2018 $ 135 Cash collected on project during 2018 $ 105 Construction in progress, 12/31/2018 $ 207 Estimated percentage of completion during 2018 60 % 1.How much revenue (in millions) is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT