Question

2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes...

2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions):

Accounts receivable, 12/31/2018 (from construction progress billings) $ 37.5
Actual construction costs incurred in 2018 $ 135
Cash collected on project during 2018 $ 105
Construction in progress, 12/31/2018 $ 207
Estimated percentage of completion during 2018 60 %

1.How much revenue (in millions) is recognized in 2019?

2. what is the net construction asset at 12/31/2018

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Dear Student, Thanks for Using Chegg, Please find below the answer and give a thumbs up.

Revenue (in millions) is recognized in 2019:

Construction in progress = actual costs incurred + gross profit recognized
$207=$135+X
X=$72
Therefore, the amount of gross profit on the project recognized by CCC during 2016 = $72
Net Construction Asset at 12/31/2018:
Billings - Cash collections = Accounts Receivables
Billings = Cash Collections + Accounts Receivables
Billings = $105+$37.5
Billings=$142.5
Add a comment
Know the answer?
Add Answer to:
2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • n 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is...

    n 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $1,600,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2016, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 30,000 Construction in progress $ 100,000 Less: Billings on construction contract (94,000 ) Cost and profit of uncompleted contracts in excess of billings 6,000 Income...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...

  • n 2021, Short Construction began construction work under a four-year contract. The contract price is $2,000,000....

    n 2021, Short Construction began construction work under a four-year contract. The contract price is $2,000,000. Short recognizes revenue over time according to percentage of completion method. The balance sheet shows the following accounts at the end of 2021: A/R of $40,000, Construction in Progress of $200,000, Less: Billings on Construction Contract of $170,000. The income statement shows Income on the contract of $30,000 at the end of 2021. What was the total estimated cost of the project at the...

  • Prachce Problem 9 In Year 1, Amber Construction Corporation began construction work under a three-year contract....

    Prachce Problem 9 In Year 1, Amber Construction Corporation began construction work under a three-year contract. The contract price is $1,610,000. Long uses the percentage-of-completion method for financial reporting purposes. The financial statement presentation relating to this contract at December 31, year 1, is as follows: Balance Sheet $30,000 Accounts receivable (from construction progress billings) Construction in progress Less: Billings on Construction Contract $100,000 (93,000) 7,000 Cost of uncompleted contracts in excess of billings Income Statement $24,000 Income (before tax)...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimat...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,420,000. During 2018, costs of $2,140,000 were incurred with estimated costs of $4,140,000 yet to be incurred. Billings of $2,640,000 were sent, and cash collected was $2,390,000. In 2019, costs incurred were $2,640,000 with remaining costs estimated to be $3,810,000. 2019 billings were $2,890,000 and $2,615,000 cash was collected. The project was completed in 2020 after additional costs of...

  • 1) Indiana Co. began a construction project in 2021 with a contract price of $150 million...

    1) Indiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. In 2022, Indiana incurred additional costs of $58.5 million and estimated an additional $40.5 million in costs to complete the project. Required: Compute the % complete along with the revenue and gross profit to...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on...

    Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The bullding was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates...

    Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT