Question

Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 220 points Complete this question by entering your answers in the tabs below. eBook Req 1 and 2 Req 3 Print References 1. CompCheck my w 10 balance sheet at the end of 2021 and 2022 as either cost in excess of billings or billings in excess of costs.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Requirement -1 2021 2022 2023
Contract price $                                   4,000,000 $                                                                          4,000,000 $4,000,000
Actual costs to date $                                       350,000 $                                                                          2,500,000 $4,250,000
Estimated costs to complete $                                   3,150,000 $                                                                          1,700,000 $              -  
Total estimated costs $                                   3,500,000 $                                                                          4,200,000 $4,250,000
Estimated gross profit
   (actual in 2023) $                                       500,000 $                                                                            -200,000 $ -250,000
Gross profit (loss) recognized:
Year 2021 $                                                 -  
Year 2022 $                                     -200,000
Year 2023 $                                       -50,000
Requirement -2
Gross profit (loss) recognized:
2021 ($4,000,000*10%)-$350,000 $                                                                                50,000
     
2022 ($200,000)-$50,000 $                                                                            -250,000
2023 ($250,000)-($2,00,000) $                                                                              -50,000
Requirement -3
Balance Sheet
Year 2021 Year 2022
Current Assets:
Costs less Loss ($2,300,000) in excess of billing $2,170,000 $                                                                              130,000
Current Liabilities:
Billings ($720,000) in excess of cost and profit $400,000 $                                       320,000

Please up vote. Thanks!

Add a comment
Know the answer?
Add Answer to:
Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on...

    Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The bullding was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company,...

    Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,720,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...

  • I need help completing this. Thank you!! Saved Help Save & Exit Submi Check my work...

    I need help completing this. Thank you!! Saved Help Save & Exit Submi Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,660,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated...

  • Hello, Can you please help me with this problem and give an explanation for the required...

    Hello, Can you please help me with this problem and give an explanation for the required tabs (1,2 and 3)? Thank you Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,140,000. Curtiss concludes that the contract does not...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT