req 1 | to be recognised | ||
2018 | 0 | ||
2019 | $ (270,000) | ||
2020 | $ (57,000) | ||
ques 2 | |||
expected profit * percentage of completion (unless there is loss) | |||
2018 | 760000*0.1 | 76000 | |
2019 | -270000 | $ (346,000) | |
2020 | -327000 | $ (57,000) | |
req 2 | |||
2018 | $ 76,000 | ||
2019 | $ (346,000) | ||
2020 | $ (57,000) | ||
ques 3 | |||
2018 | 2019 | ||
current assets | |||
costs less loss in excess of billings | |||
2814000+-270000-2130000 | $ 414,000 | ||
current liabilties | |||
Billings in excess of costs | $ 285,000 | ||
727000-366000-76000 |
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...
Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...
Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The bullding was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,720,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...
I need help completing this. Thank you!! Saved Help Save & Exit Submi Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,660,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated...
Hello, Can you please help me with this problem and give an explanation for the required tabs (1,2 and 3)? Thank you Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,140,000. Curtiss concludes that the contract does not...