Answer: 1 Does not qualify for revenue recognized over time. | ||||
Year | 2021 | 2022 | 2023 | |
Cost incurred to date | $ 370,000 | $ 2,982,000 | $ 5,031,000 | |
Estimated costs to complete | $ 3,330,000 | $ 1,988,000 | $ - | |
Total estimated costs | $ 3,700,000 | $ 4,970,000 | $ 5,031,000 | |
Contract price | $ 4,660,000 | $ 4,660,000 | $ 4,660,000 | |
Less: Total estimated costs | $ 3,700,000 | $ 4,970,000 | $ 5,031,000 | |
Estimated gross profit (loss) | $ 960,000 | $ (310,000) | $ (371,000) | |
Gross profit and sales revenue would be recognized when contract is completed. However, loss would be recognized immediately. | ||||
Year | 2021 | 2022 | 2023 | Total |
Gross profit (loss) recognized (Answer 1) | $ - | $ (310,000) | $ (61,000) | $ (371,000) |
Answer: 2 Does qualify for revenue recognized over time. | ||||
Year | 2021 | 2022 | 2023 | Total |
Total estimated costs | $ 3,700,000 | $ 4,970,000 | $ 5,031,000 | |
Contract price | $ 4,660,000 | $ 4,660,000 | $ 4,660,000 | |
Multiply: Percentage of compilation | 10% | 60% | 100% | |
Revenue recognized till the date | $ 466,000 | $ 2,796,000 | $ 4,660,000 | |
Revenue recognized up to earlier year | $ 0 | $ 466,000 | $ 2,796,000 | |
Revenue recognized in current year | $ 466,000 | $ 2,330,000 | $ 1,864,000 | $ 4,660,000 |
Cost incurred to date | $ 370,000 | $ 2,982,000 | $ 5,031,000 | |
Cost incurred during the year | $ 370,000 | $ 2,612,000 | $ 2,419,000 | $ 5,401,000 |
When Total estimated costs is belows the total contract value | ||||
Revenue recognized in current year | $ 466,000 | |||
Less: cost incurred during the year | $ 370,000 | |||
Gross profit recognition | $ 96,000 | |||
When Total estimated costs is above the total contract value | ||||
Contract price | $ 4,660,000 | $ 4,660,000 | ||
Less: Total estimated costs | $ 4,970,000 | $ 5,031,000 | ||
Estimated gross profit (loss) | $ (310,000) | $ (371,000) | ||
Less: Gain of prior period | $ (96,000) | |||
Add: Prior perio's Estimated gross loss | $ 310,000 | |||
Gross profit (loss) recognition | $ 96,000 | $ (406,000) | $ (61,000) | $ (371,000) |
Answer: 3 Balance sheet Does qualify for revenue recognized over time. | ||
Balance Sheet | 2021 | 2022 |
Current assets: | ||
Costs less loss in excess of billings | $ 282,000 | |
Current liabilities: | ||
Billings in excess of costs and profit | $ 265,000 | |
Calcuation | ||
Cost incurred to date | $ 370,000 | $ 2,982,000 |
Estimated loss , if gain arise then check Gross profit as per part 2 | $ 96,000 | $ (310,000) |
Total | $ 466,000 | $ 2,672,000 |
Cumulative Billings | $ 731,000 | $ 2,390,000 |
Current assets (Current liabilities) | $ (265,000) | $ 282,000 |
I need help completing this. Thank you!! Saved Help Save & Exit Submi Check my work...
Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,720,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...
Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...
Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The bullding was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...
Hello, Can you please help me with this problem and give an explanation for the required tabs (1,2 and 3)? Thank you Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,140,000. Curtiss concludes that the contract does not...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Fix Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9] Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The...