Question

Saved Help Save & Exit Submi Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelr
1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes
Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the baI need help completing this. Thank you!!
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Answer: 1   Does not qualify for revenue recognized over time.
Year 2021 2022 2023
Cost incurred to date $         370,000 $         2,982,000 $        5,031,000
Estimated costs to complete $     3,330,000 $         1,988,000 $                       -  
Total estimated costs $     3,700,000 $         4,970,000 $        5,031,000
Contract price $     4,660,000 $         4,660,000 $        4,660,000
Less: Total estimated costs $     3,700,000 $         4,970,000 $        5,031,000
Estimated gross profit (loss) $         960,000 $           (310,000) $         (371,000)
Gross profit and sales revenue would be recognized when contract is completed. However, loss would be recognized immediately.
Year 2021 2022 2023 Total
Gross profit (loss) recognized (Answer 1) $                     -   $           (310,000) $           (61,000) $   (371,000)
Answer: 2   Does qualify for revenue recognized over time.
Year 2021 2022 2023 Total
Total estimated costs $     3,700,000 $         4,970,000 $        5,031,000
Contract price $     4,660,000 $         4,660,000 $        4,660,000
Multiply: Percentage of compilation 10% 60% 100%
Revenue recognized till the date $         466,000 $         2,796,000 $        4,660,000
Revenue recognized up to earlier year $                      0 $             466,000 $        2,796,000
Revenue recognized in current year $         466,000 $         2,330,000 $        1,864,000 $ 4,660,000
Cost incurred to date $         370,000 $         2,982,000 $        5,031,000
Cost incurred during the year $         370,000 $         2,612,000 $        2,419,000 $ 5,401,000
When Total estimated costs is belows the total contract value
Revenue recognized in current year $         466,000
Less: cost incurred during the year $         370,000
Gross profit recognition $           96,000
When Total estimated costs is above the total contract value
Contract price $         4,660,000 $        4,660,000
Less: Total estimated costs $         4,970,000 $        5,031,000
Estimated gross profit (loss) $           (310,000) $         (371,000)
Less: Gain of prior period $             (96,000)
Add: Prior perio's Estimated gross loss $           310,000
Gross profit (loss) recognition $           96,000 $           (406,000) $           (61,000) $   (371,000)
Answer: 3 Balance sheet Does qualify for revenue recognized over time.
Balance Sheet 2021 2022
Current assets:
Costs less loss in excess of billings $             282,000
Current liabilities:
Billings in excess of costs and profit $         265,000
Calcuation
Cost incurred to date $         370,000 $         2,982,000
Estimated loss , if gain arise then check Gross profit as per part 2 $           96,000 $           (310,000)
Total $         466,000 $         2,672,000
Cumulative Billings $         731,000 $         2,390,000
Current assets (Current liabilities) $       (265,000) $             282,000
Add a comment
Know the answer?
Add Answer to:
I need help completing this. Thank you!! Saved Help Save & Exit Submi Check my work...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company,...

    Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,720,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates...

    Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...

  • Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on...

    Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The bullding was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • Hello, Can you please help me with this problem and give an explanation for the required...

    Hello, Can you please help me with this problem and give an explanation for the required tabs (1,2 and 3)? Thank you Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,140,000. Curtiss concludes that the contract does not...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Fix Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9] Curtiss Cons...

    Fix Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9] Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT