Fix
Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9]
Curtiss Construction Company, Inc., entered into a fixed-price
contract with Axelrod Associates on July 1, 2018, to construct a
four-story office building. At that time, Curtiss estimated that it
would take between two and three years to complete the project. The
total contract price for construction of the building is
$4,000,000. Curtiss concludes that the contract does not qualify
for revenue recognition over time. The building was completed on
December 31, 2020. Estimated percentage of completion, accumulated
contract costs incurred, estimated costs to complete the contract,
and accumulated billings to Axelrod under the contract
were as follows:
At 12-31-2018 | At 12-31-2019 | At 12-31-2020 | |||||||||
Percentage of completion | 10 | % | 60 | % | 100 | % | |||||
Costs incurred to date | $ | 350,000 | $ | 2,500,000 | $ | 4,250,000 | |||||
Estimated costs to complete | 3,150,000 | 1,700,000 | 0 | ||||||||
Billings to Axelrod, to date | 720,000 | 2,170,000 | 4,000,000 | ||||||||
Required:
1. Compute gross profit or loss to be recognized as a
result of this contract for each of the three years.
2. Assuming Curtiss recognizes revenue over time
according to percentage of completion, compute gross profit or loss
to be recognized in each of the three years.
3. Assuming Curtiss recognizes revenue over time
according to percentage of completion, compute the amount to be
shown in the balance sheet at the end of 2018 and 2019 as either
cost in excess of billings or billings in excess of costs.
Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you. | ||||
Requirement -1 | 2018 | 2019 | 2020 | |
Contract price | $ 4,000,000 | $ 4,000,000 | $4,000,000 | |
Actual costs to date | $ 350,000 | $ 2,500,000 | $4,250,000 | |
Estimated costs to complete | $ 3,150,000 | $ 1,700,000 | $ - | |
Total estimated costs | $ 3,500,000 | $ 4,200,000 | $4,250,000 | |
Estimated gross profit | ||||
(actual in 2020) | $ 500,000 | $ -200,000 | $ -250,000 | |
Gross profit (loss) recognized: | ||||
Year 2018 | $ - | |||
Year 2019 | $ -200,000 | |||
Year 2020 | $ -50,000 | |||
Requirement -2 | ||||
Gross profit (loss) recognized: | ||||
2018 | ($4,000,000*10%)-$350,000 | $ 50,000 | ||
2019 | ($200,000)-$50,000 | $ -250,000 | ||
2020 | ($250,000)-($2,00,000) | $ -50,000 | ||
Requirement -3 | ||||
Balance Sheet | ||||
Year 2018 | Year 2019 | |||
Current Assets: | ||||
Costs less Loss ($2,300,000) in excess of billing $2,170,000 | $ 130,000 | |||
Current Liabilities: | ||||
Billings ($720,000) in excess of cost and profit $400,000 | $ 320,000 | |||
Fix Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9] Curtiss Cons...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...
Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The bullding was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...
Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,720,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Hello,
Can you please help me with this problem and give an explanation
for the required tabs (1,2 and 3)? Thank you
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,140,000. Curtiss concludes that the contract does not...