Question

Fix

Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9]

Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows:

At 12-31-2018 At 12-31-2019 At 12-31-2020
Percentage of completion 10 % 60 % 100 %
Costs incurred to date $ 350,000 $ 2,500,000 $ 4,250,000
Estimated costs to complete 3,150,000 1,700,000 0
Billings to Axelrod, to date 720,000 2,170,000 4,000,000


Required:
1.
Compute gross profit or loss to be recognized as a result of this contract for each of the three years.
2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years.
3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs.

Answer is complete but not entirely correct Complete this question by entering your answers in the tabs below. Req 3 Req 1 an

Answer is complete but not entirely correct. Complete this question by entering your answers in the tabs below. Req 1 and 2 R

Answer is complete but not entirely correct Complete this question by entering your answers in the tabs below. Req 3 Req 1 and 2 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. (Leave no cells blank be certain to enter "O" wherever required. Loss amounts should be indicated with a minus sign.) Show less▲ eq eq Gross Profit (Loss) Recognized Over Time Gross Profit (Loss) Year Recognized letion 2018 50,000 (250,000) 2019 (200,000) $ (50,000) S (50,000) 2020 (250,000) Total project profit (loss)S (250,000)
Answer is complete but not entirely correct. Complete this question by entering your answers in the tabs below. Req 1 and 2 Rea 3 Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs. 2018 Balance Sheet (Partial) 2019 Current assets: Costs less loss in excess of billings $ 30,000 Current liabilities: Billings in excess of costs and profit 320,000 Reg 1 and 2
1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you.
Requirement -1 2018 2019 2020
Contract price $                                   4,000,000 $                                                                          4,000,000 $4,000,000
Actual costs to date $                                       350,000 $                                                                          2,500,000 $4,250,000
Estimated costs to complete $                                   3,150,000 $                                                                          1,700,000 $              -  
Total estimated costs $                                   3,500,000 $                                                                          4,200,000 $4,250,000
Estimated gross profit
   (actual in 2020) $                                       500,000 $                                                                            -200,000 $ -250,000
Gross profit (loss) recognized:
Year 2018 $                                                 -  
Year 2019 $                                     -200,000
Year 2020 $                                       -50,000
Requirement -2
Gross profit (loss) recognized:
2018 ($4,000,000*10%)-$350,000 $                                                                                50,000
     
2019 ($200,000)-$50,000 $                                                                            -250,000
2020 ($250,000)-($2,00,000) $                                                                              -50,000
Requirement -3
Balance Sheet
Year 2018 Year 2019
Current Assets:
Costs less Loss ($2,300,000) in excess of billing $2,170,000 $                                                                              130,000
Current Liabilities:
Billings ($720,000) in excess of cost and profit $400,000 $                                       320,000
Add a comment
Know the answer?
Add Answer to:
Fix Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9] Curtiss Cons...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...

  • Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates...

    Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...

  • Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on...

    Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The bullding was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...

  • Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company,...

    Chapter 06 0 Saved Help Save & Exit Submit Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,720,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Hello, Can you please help me with this problem and give an explanation for the required...

    Hello, Can you please help me with this problem and give an explanation for the required tabs (1,2 and 3)? Thank you Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,140,000. Curtiss concludes that the contract does not...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT