Question

Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to...

Question:

Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to recognize gross profit in the first year usually is determined by measuring:

a.

costs incurred in the first year, divided by estimated remaining costs to complete the project.

b.

costs incurred in the first year, divided by estimated total cost of the completed project.

c.

costs incurred in the first year, divided by estimated gross profit.

d.

none of the above.

  

2.As of December 31, 2018, Cady Corporation has one construction job for which the construction in progress account has a balance of $20,000 and the billings on construction contract account has a balance of $14,000. Cady has another construction job for which the construction in progress account has a balance of $3,000 and the billings on construction has a balance of $5,000. On the December 31, 2018 Balance Sheet, Cady Corporation will report:

a.

Billings in excess of costs and profits, $6,000.

b.

Billings in excess of costs and profits, $4,000.

c.

Costs and profits in excess of billings, $4,000.

d.

Costs and profits in excess of billings, $6,000.

  

3. Handler Company is an established manufacturer of equipment used in the construction industry. Handler has the following arrangement with Chai Company.·     

. Chai purchases equipment from Handler for a price of $2,000,000 and chooses Handler to do the installation. Handler charges the same price for the equipment irrespective of whether it does the installation or not. (Some companies do the installation themselves because they either prefer their own employees to do the work or because or relationships with other customers). The installation service included in the arrangement is estimated to have a standalone price of $20,000.

.The standalone selling price of the training session is estimated at $50,000. Other companies can also perform these services.

.Chai is obligated to pay Handler the $2,000,000 upon the delivery and installation of the equipment.

. Handler delivers the equipment on September 1, 2017, and completes the installation of the equipment on November 1, 2017 (transfer of control is complete). Training related to the equipment starts once the installation is completed and lasts for 1 year.

a. How many performance obligations are in this contract?_________________

b. What is the transaction price?__________________

c. What is the allocated transaction price for the equipment?______________

1 0
Add a comment Improve this question Transcribed image text
Answer #1

Q1. The correct answer is , b) costs incurred in the first year, divided by estimated total cost of the completed project.

It is quiet logical that you must recognized revenue upto the extent you have incurred cost.

Eg - the total cost of project is 10 and future income from project is 15 , In first year you incurred 2 then revenue recognized will be proportionate i.e. 2 * 10/15 = 3

Q2. The right anwer is , c) Costs and profits in excess of billings, $4,000.

The Costs and profits in excess of billings is an asset. it simply means you are entitled to book higher amount (20,000+3,000) but have raised less bills (14,000+5,000) and the other case i.e. Billings in excess of costs and profits is vice-versa.

Q3. This case will be better to understand if you refer IFRS -15 Revenue from Contract with Customer .

In this scenario first let me summarize it for you -

1. The contract is completed when the installation is complete and The total Cost is of Equipment + Installation cost because 200,000 is charged whether installation services is taken from Handler or not.

2. The Training cost 50,000 is readily available in the market and can be taken independently but Chai chooses to take it from Handler.

3. There is no where mentioned in the question that Handler is charging any additional consideration for training services but we are assuming that 200,000 does not includes the charges of training because It is mentioned that Chai is obligated to pay Handler the $2,000,000 upon the delivery and installation of the equipment.

a. There are two performance obligation i.e Equipment delivery and Installation services.

b. The transaction price = 200,000.

c. The allocated transaction price for equipment is 180,000 &

the allocated transaction price for installation will be 20,000.

Add a comment
Know the answer?
Add Answer to:
Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Handler Company is an experienced manufacturer of equipment used in the construction industry

    4. Handler Company is an experienced manufacturer of equipment used in the construction industry. Handler's products range from small to large individual pieces of automated machinery to complex systems containing numerous components. Unit selling prices range from $600,000 to $4,000,000 and are quoted inclusive of installation and training. The installation process does not involve changes to the features of the equipment and does not require proprietary information about the equipment in order for the installed equipment to perform to specifications....

  • Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started...

    Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:                                             2017                                    2018 Current year construction costs                                       $3,300,000                             $ 620,000 Estimated remaining costs to complete                              600,000                                   -0- Current year billings                                                            3,100,000                              1,400,000 Current year collections                                                    3,000,000                                1,500,000 Required: Calculate the following amounts for each method:               Completed Percentage-of Contract Completion                                   2017      2018    2017    2018 a) Gross Profit                                                                                              $             $           $          ...

  • Question6. Long-term contract based on percentage of completion method (32 (4) Prepare journal entry to record...

    Question6. Long-term contract based on percentage of completion method (32 (4) Prepare journal entry to record gross profit for 2017(6 points) (5) Show at end of 2017 and 2018, what are the balance af CIP ( points) points) lim's Construction Co. has a $85,000,000 contract to build a new football stadium The project began on January 1, 2016 with an expected completion date of October 31, 2018. The following table provides infomation gathered during the construction period. Jim uses the...

  • 1. Assurning a long-term construction project makes an overall profit, during the interim years, percentage of...

    1. Assurning a long-term construction project makes an overall profit, during the interim years, percentage of completion method accounting has impact on construction company's: Income Statement ONLY X Balance Sheet ONLY BOTH Income Statement and Balance Sheet None of the above 2. When a company write-off a bad debt under GAAP, it has impact on this company's: Income Statement ONLY Balance Sheet ONLY BOTH Income Statement and Balance Sheet Cash Flow Statement ONLY х 3. For a construction company working...

  • Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work...

    Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 -0- Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017...

  • Exercise 18-36 Marin Construction Company uses the percentage of completion method of accounting in 2017, Marin...

    Exercise 18-36 Marin Construction Company uses the percentage of completion method of accounting in 2017, Marin began work under contract E2-02, which provided for a contract price of 52,195,000. Other details follow 2017 2018 Costs incurred during the year 5695,310 $1,404,000 Estimated costs to complete, as of December 31921,690 0 Billings to date 426,000 2,195,000 Collections during the year 352,000 1,475,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in...

  • Hamilton Construction Company uses the percentage-of-completion method of accounting. In 2020, Hamilton began work on the...

    Hamilton Construction Company uses the percentage-of-completion method of accounting. In 2020, Hamilton began work on the construction of a hospital, which provides for a contract price of $2,195,000. Other details follow: 20XO 20X1 Costs incurred during the year 637,600 1,000,000 Total estimated cost 1,594,000 1,637,600 Billings during the year 427,000 2,195,000 Collections during the year 343,000 1,509,000 What portion of the total contract price would be recognized as revenue in 20x0? 2,195,000 878,000 1,097,500 427,000 343,000

  • Griffin Constructors, Inc. has consistently used the percentage-of-completion method of recognizing income. In 2018, Gri...

    Griffin Constructors, Inc. has consistently used the percentage-of-completion method of recognizing income. In 2018, Griffin started work on a $49,000,000 construction contract that was completed in 2019. The following information was taken from Griffin's 2018 accounting records: Progress billings $15,400,000 Costs incurred 14,700,000 Collections 9,600,000 Estimated costs to complete 29,400,000 How much was the Company over/under billed for the year ended December 31, 2018 (round percentage complete to 2 decimal points (example .513655555 = .51))? a. 770,000 b. 1,633,333 c....

  • Percentage of Completion Problem: The Nifty Construction Company entered into a long-term contract in 2013. The...

    Percentage of Completion Problem: The Nifty Construction Company entered into a long-term contract in 2013. The contract price was $1,600,000, and the company initially estimated the total cost of the project to be $1,150,000. The following data pertains to the three years that the contract was in process: 2013 2014 2015 $224,000 $936,000 $1,280,000 Costs incurred to date Estimated costs to complete Billings to date Collections to date 896,000 264,000 0 200,000 1,200,000 1,600,00 170,000 1,070,000 1,500000 Using the percentage...

  • When using the percentage of completion method, the company - recognizes revenues and gross profit each...

    When using the percentage of completion method, the company - recognizes revenues and gross profit each period during the contract. - accumulates construction costs only in an inventory account (Construction in Process). - accumulates progress billings in an inventory account (Construction in Process). - recognizes revenues and gross profit only when the contract is completed.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT