2018 | 2019 | 2020 | ||||
Contract price | $ 1,600,000 | $ 1,600,000 | $ 1,600,000 | |||
Actual costs to date | $ 224,000 | $ 936,000 | $ 1,280,000 | |||
Estimated costs | $ 896,000 | $ 264,000 | ||||
total estimated costs | $ 1,120,000 | $ 1,200,000 | $ 1,280,000 | |||
Estimated gross profit (loss) | $ 480,000 | $ 400,000 | $ 320,000 | |||
revenue recognition | ||||||
2018:(224000/1120000)= | 20.00% | |||||
20%*1600000= | $ 320,000 | |||||
2019:(936000/1200000)= | 78.00% | |||||
(78%*1600000)-320000= | $ 928,000 | |||||
2020:1600000-320000-928000 | $ 352,000 | |||||
Gross profit (loss) recognition: | ||||||
2018:320000-224000= | $ 96,000 | |||||
2019:928000-(936000-224000)= | $ 216,000 | |||||
2020:352000-(1280000-936000)= | $ 8,000 | |||||
Journal entries | ||||||
2018 | 2019 | 2020 | ||||
Debit | Credit | Debit | Credit | Debit | Credit | |
Construction in progress | $ 224,000 | $ 712,000 | $ 344,000 | |||
Various accounts | $ 224,000 | $ 712,000 | $ 344,000 | |||
Accounts receivable | $ 200,000 | $ 1,200,000 | $ 1,600,000 | |||
Billings on construction contract | $ 200,000 | $ 1,200,000 | $ 1,600,000 | |||
Cash | $ 170,000 | $ 1,070,000 | $ 1,500,000 | |||
Accounts receivable | $ 170,000 | $ 1,070,000 | $ 1,500,000 | |||
Construction In progress | $ 96,000 | $ 216,000 | $ 8,000 | |||
Cost of construction | $ 224,000 | $ 712,000 | $ 344,000 | |||
Revenue from long term contracts | $ 320,000 | $ 928,000 | $ 352,000 |
Percentage of Completion Problem: The Nifty Construction Company entered into a long-term contract in 2013. The...
At the beginning of 2013, the Harding Construction Company received a contract to build an office building for $10 million. Harding will construct the building according to specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will bill the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2013 2014 2015 Cost incurred during the year $2,300,000...
Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building at a contract price of $5,400,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2014. Information relating to the costs and billings for this contract is as follows: 2014 2012 $1,500,000 2,500,000 2,200,000 2,000,000 2013 $4,600,000 $2,640,000 1,760,000 4,000,000 3,500,000 Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date -0-...
why the gross profit of 2014 is -766667 On February 1, 2013, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2013, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent and cash collected was $2,250,000 In 2014, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2014 billings were $2,750,000 and $2,475,000 cash was collected. The project...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, lo construct a four- story office building. At that time, Curtiss estimated that it would take belween two and three years to complete the project. The total contract price for construction of the building is $5.080,000. Curliss concludes that the contract does not qually for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract...
During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...