Question

At the beginning of 2013, the Harding Construction Company received a contract to build an office...

At the beginning of 2013, the Harding Construction Company received a contract to build an office building for $10 million. Harding will construct the building according to specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will bill the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows:

2013

2014

2015

Cost incurred during the year

$2,300,000

$3,600,000

$2,100,000

Estimated costs to complete

5,300,000

2,000,000

0

Billings during the year

1,700,000

4,000,000

4,300,000

Cash collections during the year

1,600,000

3,600,000

4,300,000

  

Calculate the following:

Gross profit recognized:

Percentage of completion Method

2013

2014

2015

Total gross profit:

Please show all the process and correct answers

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer------

Gross profit recognized: Percentage of completion Method Completed contract Method
2013 $       7,26,316
2014 $       8,42,039
2015 $       4,31,646 $     20,00,000
Total gross profit $     20,00,000 $     20,00,000

Working for percentage of completion

Working 2013 2014 2015
A Contract Price $ 10,000,000 $ 10,000,000 $ 10,000,000
B Cost Incurred to Date $ 2,300,000 $ 5,900,000 $ 8,000,000
C Estimated cost yet to be incurred to complete the contract $ 5,300,000 $ 2,000,000 $ 0
D = B+C Total Cost $ 7,600,000 $ 7,900,000 $ 8,000,000
E = (D/B) x 100 % of Complition 30% 75% 100%
F = A x E Revenue to date $ 3,026,316 $ 7,468,354 $ 10,000,000
G Revenue of Previous year $ 0 $ 3,026,316 $ 7,468,354
H = F - G Net Revenue this year $ 3,026,316 $ 4,442,039 $ 2,531,646
I Cost to date $ 2,300,000 $ 5,900,000 $ 8,000,000
J Cost to date of previous year $ 0 $ 2,300,000 $ 5,900,000
K = I - J Net Cost for the year $ 2,300,000 $ 3,600,000 $ 2,100,000
L = H - K Gross Profits $ 726,316 $ 842,039 $ 431,646

In case of Completed contract method all revenues and gross profit is recognized at the time the contract is complete.

Add a comment
Know the answer?
Add Answer to:
At the beginning of 2013, the Harding Construction Company received a contract to build an office...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • why the gross profit of 2014 is -766667 On February 1, 2013, Arrow Construction Company entered...

    why the gross profit of 2014 is -766667 On February 1, 2013, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2013, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent and cash collected was $2,250,000 In 2014, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2014 billings were $2,750,000 and $2,475,000 cash was collected. The project...

  • On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...

  • Percentage of Completion Problem: The Nifty Construction Company entered into a long-term contract in 2013. The...

    Percentage of Completion Problem: The Nifty Construction Company entered into a long-term contract in 2013. The contract price was $1,600,000, and the company initially estimated the total cost of the project to be $1,150,000. The following data pertains to the three years that the contract was in process: 2013 2014 2015 $224,000 $936,000 $1,280,000 Costs incurred to date Estimated costs to complete Billings to date Collections to date 896,000 264,000 0 200,000 1,200,000 1,600,00 170,000 1,070,000 1,500000 Using the percentage...

  • 1) A construction company entered into a fixed-price contract to build an office building for $20...

    1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...

  • Black Sea Construction Company has a contract to construct a $6,000,000 oil rig at an estimated...

    Black Sea Construction Company has a contract to construct a $6,000,000 oil rig at an estimated cost of $5,300,000. The contract is to start in July 2017, and the oil rig is to be completed in October 2019. The following data pertain to the construction period. 2017    2018    2019 Costs to date $1,325,000 $3,720,000 $6,300,000 Estimated costs to complete 3,975,000 2,480,000 — Progress billings during the year 1,200,000 3,200,000 1,600,000 Cash collected during the year 1,000,000 2,340,000 2,660,000 What amount...

  • Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building...

    Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building at a contract price of $5,400,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2014. Information relating to the costs and billings for this contract is as follows: 2014 2012 $1,500,000 2,500,000 2,200,000 2,000,000 2013 $4,600,000 $2,640,000 1,760,000 4,000,000 3,500,000 Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date -0-...

  • Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road...

    Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara Countyfor $10,000,000. The road was completed in 201 contract is as follows: 8. Information related to the 2018 2016 2,400,000 3,600,000 2,200,00 5,600,000 2,000,000 4,000,000 4,000,000 ,800,000 3,600,000 4,600,000 2017 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2,000,000 Westgate recognizes revenue over time according to percentage of...

  • A construction company entered into a fixed price contract to build an office building for $16...

    A construction company entered into a fixed price contract to build an office building for $16 milion. Construction costs incurred during the first year were $3 million and estimated costs to complete at the end of the year were $7 million. The company recognizes revenue over time according to percentage of completion How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.)...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...

  • A construction company entered into a fixed price contract to build an office building for $46...

    A construction company entered into a fixed price contract to build an office building for $46 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT