1)
A construction company entered into a fixed-price contract to
build an office building for $20 million. Construction costs
incurred during the first year were $6 million and estimated costs
to complete at the end of the year were $9 million.
The building was completed during the second year. Construction
costs incurred during the second year were $10 million.
How much revenue and gross profit or loss will the company
recognize in the first and second year if it recognizes revenue
upon contract completion?
2)
Franklin Construction entered into a fixed-price contract to
build a freeway-connecting ramp for $30 million. Construction costs
incurred in the first year were $16 million and estimated remaining
costs to complete at the end of the year were $17 million.
How much gross profit or loss will Franklin recognize in the first
year if it recognizes revenue over time according to percentage of
completion method?
How much gross profit or loss will Franklin recognize in the first year applying the completed contract method?
Comment below if you have any query i will solve it asap !! thanks
1) A construction company entered into a fixed-price contract to build an office building for $20...
A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...
A construction company entered into a fixed-price contract to build an office building for $44 million. Construction costs incurred during the first year were $14 million and estimated costs to complete at the end of the year were $21 million. The building was completed during the second year. Construction costs incurred during the second year were $22 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...
Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $30 million. Construction costs incurred in the first year were $16 million and estimated remaining costs to complete at the end of the year were $17 million. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion method? How much gross profit or loss will Franklin recognize in the first year applying the...
A construction company entered into a fixed-price contract to build an office building for $48 million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...
A construction company entered into a fixed-price contract to build an office building for $10 million. Construction costs incurred during the first year were $2 million and estimated costs to complete at the end of the year were $3 million. The building was completed during the second year. Construction costs incurred during the second year were $4 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...
Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $46 million. Construction costs incurred in the first year were $36 million and estimated remaining costs to complete at the end of the year were $23 million. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion method? (Enter your answer in millions.) Gross loss million How much gross profit or loss will...
Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $42 million. Construction costs incurred in the first year were $32 million and estimated remaining costs to complete at the end of the year were $21 million. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion method? (Enter your answer in millions.) million How much gross profit or loss will Franklin recognize...
2. Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $58 million. Construction costs incurred in the first year were $48 million and estimated remaining costs to complete at the end of the year were $29 million. a. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion method? (Enter your answer in millions.) b. How much gross profit or loss will...
A construction company entered into a fixed price contract to build an office building for $46 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.)...
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue