Year 1 | Year 2 | |
Revenue | 48*18/(18+27) = $19.20 million | 48-$19.20 million = $28.80 |
Gross profit | $19.20 million - 18 = $1.20 million | $28.80-28 = $0.80 million |
A construction company entered into a fixed-price contract to build an office building for $48 million....
A construction company entered into a fixed-price contract to build an office building for $10 million. Construction costs incurred during the first year were $2 million and estimated costs to complete at the end of the year were $3 million. The building was completed during the second year. Construction costs incurred during the second year were $4 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...
A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...
A construction company entered into a fixed-price contract to build an office building for $44 million. Construction costs incurred during the first year were $14 million and estimated costs to complete at the end of the year were $21 million. The building was completed during the second year. Construction costs incurred during the second year were $22 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...
1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...
Brief Exercise 6-35 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] A construction company entered into a fixed-price contract to build an office building for $48 million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million How much revenue and gross profit or loss will the company...
Brief Exercise 5-33 Long-term contract; revenue recognition upon completion [LO5-9] A construction company entered into a fixed-price contract to build an o million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. ng How much revenue and gross profit or loss will the company recognize in the...
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue
A construction company entered into a fixed-price contract to build an office building for $46 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue
A construction company entered into a fixed price contract to build an office building for $46 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.)...
A construction company entered into a fixed price contract to build an office building for $16 milion. Construction costs incurred during the first year were $3 million and estimated costs to complete at the end of the year were $7 million. The company recognizes revenue over time according to percentage of completion How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.)...