Question

Brief Exercise 6-35 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] A construction company entered int

0 0
Add a comment Improve this question Transcribed image text
Answer #1

YEAR 1

ESTIMATED COST = $48 MILLION

COST INCURRED = $18 MILLION

THERE FORE ;; ESTIMATED COST - COST INCURRED

48-18 = $30 MILLION

THAT IS A PROFIT OF $30 MILLION

YEAR 2

ESTIMATED COST = $27 MILLION

COST INCURRED = $28 MILLION

THERE FORE ;; ESTIMATED COST - COST INCURRED

27-28 = -$1 MILLION

THAT IS A LOSS OF $1 MILLION

YEAR 1 (In Million) YEAR 2 (In Million)
REVENUE $30 0
PROFIT AND LOSS PROFIT $30 LOSS $ 1



Add a comment
Know the answer?
Add Answer to:
Brief Exercise 6-35 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] A construction company entered into...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Brief Exercise 5-33 Long-term contract; revenue recognition upon completion [LO5-9] A construction company entered into a...

    Brief Exercise 5-33 Long-term contract; revenue recognition upon completion [LO5-9] A construction company entered into a fixed-price contract to build an o million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. ng How much revenue and gross profit or loss will the company recognize in the...

  • A construction company entered into a fixed-price contract to build an office building for $48 million....

    A construction company entered into a fixed-price contract to build an office building for $48 million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $10 million....

    A construction company entered into a fixed-price contract to build an office building for $10 million. Construction costs incurred during the first year were $2 million and estimated costs to complete at the end of the year were $3 million. The building was completed during the second year. Construction costs incurred during the second year were $4 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June...

    Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated...

  • 1) A construction company entered into a fixed-price contract to build an office building for $20...

    1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...

  • A construction company entered into a fixed-price contract to build an office building for $20 million....

    A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $44 million....

    A construction company entered into a fixed-price contract to build an office building for $44 million. Construction costs incurred during the first year were $14 million and estimated costs to complete at the end of the year were $21 million. The building was completed during the second year. Construction costs incurred during the second year were $22 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO6-8,...

    Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO6-8, 6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2021, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2022, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2022 billings...

  • Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] In 2021, the Westgate Construction Company...

    Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,976,000 5, 624,000 1,600,000 1,400,000 2022 $3,420,000 2,204,000 3,796,000 3,200,000 2023 $2,424, 400 0...

  • Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On...

    Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2,130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2,630,000 with remaining costs estimated to be $3,795,000. 2022 billings were $2,880,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT