Question

Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] In 2021, the Westgate Construction Compan

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Requirement 1 Amount in $
Particulars 2021 2022 2023
Cost incurred in till previous year 0 1976000 5396000
ADD Cost incurred during the Year 1976000 3420000 2424400
Total Cost Incurred till date 1976000 5396000 7820400
ADD Estimated Cost to be incurred 5624000 2204000 0
Total estimated cost to be incurred 7600000 7600000 7820400
Percentage of Completion (A) 26% 71% 100%
(Cost incurred till date / Total Estimated Cost)
Total Revenue (B) 10000000 10000000 10000000
Total Revenue Recognized (A* B) 2600000 7100000 10000000
LESS Revenue Recognized in Previous Year 0 2600000 7100000
Revenue Recognized in Current Year 2600000 4500000 2900000
Particulars 2021 2022 2023
Revenue 2600000 4500000 2900000
LESS Cost Incurred 1976000 3420000 2424400
Gross Profit 624000 1080000 475600
Requirement 2A
Date Particulars Debit Credit
2021 Construction in Progress $1,976,000
       Various Accounts $1,976,000
2021 Accounts Receivable $1,600,000
      Billings on Construction Contract $1,600,000
2021 Cash $1,400,000
       Accounts Receivable $1,400,000
Requirement 2B
Date Particulars Debit Credit
2022 Construction in Progress $3,420,000
       Various Accounts $3,420,000
2022 Accounts Receivable $3,796,000
      Billings on Construction Contract $3,796,000
2022 Cash $3,200,000
       Accounts Receivable $3,200,000
Requirement 2C
Date Particulars Debit Credit
2023 Construction in Progress $2,424,400
       Various Accounts $2,424,400
2023 Accounts Receivable $4,604,000
      Billings on Construction Contract $4,604,000
2023 Cash $5,400,000
       Accounts Receivable $5,400,000
2023 Cost of Construction $7,820,400
Construction in Progress $2,179,600
       Revenue from Long Term Contracts $10,000,000
Requirement 3
Balance Sheet (Partial) 2021 2022
Current Assets:
Accounts Receivable $200,000 $596,000
Construction in Progress $1,976,000 $5,396,000
Less: Billings $1,600,000 $5,396,000
Costs in excess of Billings $376,000 $0
Requirement 4 Amount in $
Particulars 2021 2022 2023
Cost incurred in till previous year 0 2540000 6410000
ADD Cost incurred during the Year 2540000 3870000 3240000
Total Cost Incurred till date 2540000 6410000 9650000
ADD Estimated Cost to be incurred 5740000 3240000 0
Total estimated cost to be incurred 8280000 9650000 9650000
Percentage of Completion (A) 31% 66% 100%
(Cost incurred till date / Total Estimated Cost)
Total Revenue (B) 10000000 10000000 10000000
Total Revenue Recognized (A* B) 3067632.85 6642487.047 10000000
LESS Revenue Recognized in Previous Year 0 3067632.85 6642487.05
Revenue Recognized in Current Year 3067632.85 3574854.196 3357512.95
Particulars 2021 2022 2023
Revenue 3067632.85 3574854.196 3357512.95
LESS Cost Incurred 2540000 3870000 3240000
Gross Profit 527632.85 -295145.804 117512.953
Requirement 5 Amount in $
Particulars 2021 2022 2023
Cost incurred in till previous year 0 2540000 6410000
ADD Cost incurred during the Year 2540000 3870000 4110000
Total Cost Incurred till date 2540000 6410000 10520000
ADD Estimated Cost to be incurred 5740000 4240000 0
Total estimated cost to be incurred 8280000 10650000 10520000
Percentage of Completion (A) 31% 60% 100%
(Cost incurred till date / Total Estimated Cost)
Total Revenue (B) 10000000 10000000 10000000
Total Revenue Recognized (A* B) 3067632.85 6018779.343 10000000
LESS Revenue Recognized in Previous Year 0 3067632.85 6018779.34
Revenue Recognized in Current Year 3067632.85 2951146.492 3981220.66
Particulars 2021 2022 2023
Revenue 3067632.85 2951146.492 3981220.66
LESS Cost Incurred 2540000 3870000 4110000
Gross Profit 527632.85 -918853.508 -128779.34
Add a comment
Know the answer?
Add Answer to:
Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] In 2021, the Westgate Construction Company...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9) In 2021, the Westgate Construction Company...

    Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,797,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $3,096,000 5,504,000 2,600,000 2,400,000 2022 $3,870,000 1,634,000 4,366,000 4,200,000 3,034,000 3,400,000 Assume...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...

  • Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information...

    Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,975,000 $ 3,825,000 $ 1,870,000 Estimated costs to complete as of year-end 5,525,000 1,700,000 0 Billings during the year 2,500,000 4,300,000 3,200,000 Cash collections during the year 2,300,000 4,100,000 3,600,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify...

  • Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] The following information...

    Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,640,000...

  • 6 Problem 5-11 Long-term contract; revenue recognition upon completion [LO5-9) In 2018, the Westgate Construction Company...

    6 Problem 5-11 Long-term contract; revenue recognition upon completion [LO5-9) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $30,000000 The road was completed in 2020 Information related to the contract is as folows Billings during the year Cash cellections during the year 1,800,0003,690,84,600,0 SeferencesWestgate Construction uses the completed contract method of accounting for long-term construction contrects Required: 1. Calculate the amount of revenue and gross profit (oss) to be...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT