Requirement 1 | Amount in $ | ||||
Particulars | 2021 | 2022 | 2023 | ||
Cost incurred in till previous year | 0 | 1976000 | 5396000 | ||
ADD | Cost incurred during the Year | 1976000 | 3420000 | 2424400 | |
Total Cost Incurred till date | 1976000 | 5396000 | 7820400 | ||
ADD | Estimated Cost to be incurred | 5624000 | 2204000 | 0 | |
Total estimated cost to be incurred | 7600000 | 7600000 | 7820400 | ||
Percentage of Completion (A) | 26% | 71% | 100% | ||
(Cost incurred till date / Total Estimated Cost) | |||||
Total Revenue (B) | 10000000 | 10000000 | 10000000 | ||
Total Revenue Recognized (A* B) | 2600000 | 7100000 | 10000000 | ||
LESS | Revenue Recognized in Previous Year | 0 | 2600000 | 7100000 | |
Revenue Recognized in Current Year | 2600000 | 4500000 | 2900000 | ||
Particulars | 2021 | 2022 | 2023 | ||
Revenue | 2600000 | 4500000 | 2900000 | ||
LESS | Cost Incurred | 1976000 | 3420000 | 2424400 | |
Gross Profit | 624000 | 1080000 | 475600 | ||
Requirement 2A | |||||
Date | Particulars | Debit | Credit | ||
2021 | Construction in Progress | $1,976,000 | |||
Various Accounts | $1,976,000 | ||||
2021 | Accounts Receivable | $1,600,000 | |||
Billings on Construction Contract | $1,600,000 | ||||
2021 | Cash | $1,400,000 | |||
Accounts Receivable | $1,400,000 | ||||
Requirement 2B | |||||
Date | Particulars | Debit | Credit | ||
2022 | Construction in Progress | $3,420,000 | |||
Various Accounts | $3,420,000 | ||||
2022 | Accounts Receivable | $3,796,000 | |||
Billings on Construction Contract | $3,796,000 | ||||
2022 | Cash | $3,200,000 | |||
Accounts Receivable | $3,200,000 | ||||
Requirement 2C | |||||
Date | Particulars | Debit | Credit | ||
2023 | Construction in Progress | $2,424,400 | |||
Various Accounts | $2,424,400 | ||||
2023 | Accounts Receivable | $4,604,000 | |||
Billings on Construction Contract | $4,604,000 | ||||
2023 | Cash | $5,400,000 | |||
Accounts Receivable | $5,400,000 | ||||
2023 | Cost of Construction | $7,820,400 | |||
Construction in Progress | $2,179,600 | ||||
Revenue from Long Term Contracts | $10,000,000 | ||||
Requirement 3 | |||||
Balance Sheet (Partial) | 2021 | 2022 | |||
Current Assets: | |||||
Accounts Receivable | $200,000 | $596,000 | |||
Construction in Progress | $1,976,000 | $5,396,000 | |||
Less: Billings | $1,600,000 | $5,396,000 | |||
Costs in excess of Billings | $376,000 | $0 | |||
Requirement 4 | Amount in $ | ||||
Particulars | 2021 | 2022 | 2023 | ||
Cost incurred in till previous year | 0 | 2540000 | 6410000 | ||
ADD | Cost incurred during the Year | 2540000 | 3870000 | 3240000 | |
Total Cost Incurred till date | 2540000 | 6410000 | 9650000 | ||
ADD | Estimated Cost to be incurred | 5740000 | 3240000 | 0 | |
Total estimated cost to be incurred | 8280000 | 9650000 | 9650000 | ||
Percentage of Completion (A) | 31% | 66% | 100% | ||
(Cost incurred till date / Total Estimated Cost) | |||||
Total Revenue (B) | 10000000 | 10000000 | 10000000 | ||
Total Revenue Recognized (A* B) | 3067632.85 | 6642487.047 | 10000000 | ||
LESS | Revenue Recognized in Previous Year | 0 | 3067632.85 | 6642487.05 | |
Revenue Recognized in Current Year | 3067632.85 | 3574854.196 | 3357512.95 | ||
Particulars | 2021 | 2022 | 2023 | ||
Revenue | 3067632.85 | 3574854.196 | 3357512.95 | ||
LESS | Cost Incurred | 2540000 | 3870000 | 3240000 | |
Gross Profit | 527632.85 | -295145.804 | 117512.953 | ||
Requirement 5 | Amount in $ | ||||
Particulars | 2021 | 2022 | 2023 | ||
Cost incurred in till previous year | 0 | 2540000 | 6410000 | ||
ADD | Cost incurred during the Year | 2540000 | 3870000 | 4110000 | |
Total Cost Incurred till date | 2540000 | 6410000 | 10520000 | ||
ADD | Estimated Cost to be incurred | 5740000 | 4240000 | 0 | |
Total estimated cost to be incurred | 8280000 | 10650000 | 10520000 | ||
Percentage of Completion (A) | 31% | 60% | 100% | ||
(Cost incurred till date / Total Estimated Cost) | |||||
Total Revenue (B) | 10000000 | 10000000 | 10000000 | ||
Total Revenue Recognized (A* B) | 3067632.85 | 6018779.343 | 10000000 | ||
LESS | Revenue Recognized in Previous Year | 0 | 3067632.85 | 6018779.34 | |
Revenue Recognized in Current Year | 3067632.85 | 2951146.492 | 3981220.66 | ||
Particulars | 2021 | 2022 | 2023 | ||
Revenue | 3067632.85 | 2951146.492 | 3981220.66 | ||
LESS | Cost Incurred | 2540000 | 3870000 | 4110000 | |
Gross Profit | 527632.85 | -918853.508 | -128779.34 | ||
Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] In 2021, the Westgate Construction Company...
Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,797,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $3,096,000 5,504,000 2,600,000 2,400,000 2022 $3,870,000 1,634,000 4,366,000 4,200,000 3,034,000 3,400,000 Assume...
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows: 2021 2022 2023 Cost incurred during the
year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to
complete as of year-end 5,616,000 2,376,000 0 Billings during the
year 1,200,000 3,624,000 5,176,000 Cash collections during the year
1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s
contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9) [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,640,000 6,160,000...
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
2021
2022
2023
Cost incurred during the year
$
2,975,000
$
3,825,000
$
1,870,000
Estimated costs to complete as of year-end
5,525,000
1,700,000
0
Billings during the year
2,500,000
4,300,000
3,200,000
Cash collections during the year
2,300,000
4,100,000
3,600,000
Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify...
Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time (LO6-8, 6-9] The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,640,000...
6 Problem 5-11 Long-term contract; revenue recognition upon completion [LO5-9) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $30,000000 The road was completed in 2020 Information related to the contract is as folows Billings during the year Cash cellections during the year 1,800,0003,690,84,600,0 SeferencesWestgate Construction uses the completed contract method of accounting for long-term construction contrects Required: 1. Calculate the amount of revenue and gross profit (oss) to be...