Dear student, we cannot able to post solution more than four subparts of the question as per our policy. |
Answer 1 | ||||
Revenue Recognize = Cost incurred plus Gross Profit Less Gross Loss (if any) | ||||
Gross profit Recognize under completed contract method when Company completed contract. | ||||
Gross Profit from Contract = 10000000-2400000-3600000-2200000 | 1,800,000 | |||
Year | 2018 | 2019 | 2020 | |
Gross profit | 0 | 0 | 1,800,000 | |
Revenue | 2,400,000 | 3,600,000 | 4,000,000 | |
Answer 2 | ||||
Date | General Journal | Debit | Credit | |
2018 | Construction in progress | 2,400,000 | ||
Various accounts | 2,400,000 | |||
(To record cost incurred in Progress.) | ||||
2018 | Accounts receivable | 2,000,000 | ||
Billings on construction contract | 2,000,000 | |||
(To record Billings to Customer.) | ||||
2018 | Cash | 1,800,000 | ||
Accounts receivable | 1,800,000 | |||
(To record cash collected from the customer.) | ||||
2018 | No Journal entry required. | |||
2019 | Construction in progress | 3,600,000 | ||
Various accounts | 3,600,000 | |||
(To record cost incurred in Progress.) | ||||
2019 | Accounts receivable | 4,000,000 | ||
Billings on construction contract | 4,000,000 | |||
(To record Billings to Customer.) | ||||
2019 | Cash | 3,600,000 | ||
Accounts receivable | 3,600,000 | |||
(To record cash collected from the customer.) | ||||
2019 | No Journal entry required. | |||
2020 | Construction in progress | 2,200,000 | ||
Various accounts | 2,200,000 | |||
(To record cost incurred in Progress.) | ||||
2020 | Accounts receivable | 4,000,000 | ||
Billings on construction contract | 4,000,000 | |||
(To record Billings to Customer.) | ||||
2020 | Cash | 4,600,000 | ||
Accounts receivable | 4,600,000 | |||
(To record cash collected from the customer.) | ||||
2020 | Construction in progress | 1,800,000 | ||
Cost of construction | 8,200,000 | |||
Revenue from long-term contracts | 10,000,000 | |||
(To record recognize Revenue.) | ||||
Answer 3 | ||||
Partial balance sheet | ||||
2018 | 2019 | |||
Current assets | ||||
Account receivable | 200,000 | 600,000 | ||
Construction in progress | 2,400,000 | 6,000,000 | ||
Less: Billings | 2,000,000 | 6,000,000 | ||
Cost in excess of Billings | 400,000 | 0 | ||
Current liability | ||||
Answer 4 | ||||
Revenue Recognize = Cost incurred plus Gross Profit Less Gross Loss (if any) | ||||
Gross profit Recognize under the completed contract method when Company completed contract. | ||||
Gross Profit from Contract = 10000000-2400000-3800000-3200000 | 600,000 | |||
Year | 2018 | 2019 | 2020 | |
Gross profit | 0 | 0 | 600,000 | |
Revenue | 2,400,000 | 3,800,000 | 3,800,000 |
6 Problem 5-11 Long-term contract; revenue recognition upon completion [LO5-9) In 2018, the Westgate Construction Company...
Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,976,000 5, 624,000 1,600,000 1,400,000 2022 $3,420,000 2,204,000 3,796,000 3,200,000 2023 $2,424, 400 0...
Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,797,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $3,096,000 5,504,000 2,600,000 2,400,000 2022 $3,870,000 1,634,000 4,366,000 4,200,000 3,034,000 3,400,000 Assume...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...
in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2823 $2,475,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,875, eee 5.625.000 1,5ee,eee 1,3ee,eee 2022 $3,375,000 2.25e,eee 3,75e,eee 3,100,eee 4,750,000 5,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify...