In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,581,000 | $ | 2,347,000 | $ | 3,049,200 | |||
Estimated costs to complete as of year-end | 6,319,000 | 2,772,000 | 0 | ||||||
Billings during the year | 2,090,000 | 2,838,000 | 5,072,000 | ||||||
Cash collections during the year | 1,845,000 | 2,900,000 | 5,255,000 | ||||||
Westgate recognizes revenue over time according to percentage of completion.
2-a. In the journal below, complete the
necessary journal entries for the year 2018 (credit "Various
accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2020 (credit "Various accounts" for
construction costs incurred).
Then Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.
Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,581,000 | $ | 3,845,000 | $ | 3,245,000 | |||
Estimated costs to complete as of year-end | 6,319,000 | 3,145,000 | 0 | ||||||
Calculate the amount of revenue and gross profit (loss) to be
recognized in each of the three years assuming the following costs
incurred and costs to complete information. (Do not round
intermediate calculations and round your final answers to the
nearest whole dollar amount. Loss amounts should be indicated with
a minus sign.)
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,581,000 | $ | 3,845,000 | $ | 4,035,000 | |||
Estimated costs to complete as of year-end | 6,319,000 | 4,190,000 | 0 | ||||||
Percentage completion method | 2018 | 2019 | 2020 | |
Cost incurred in till previous year | 0 | 2581000 | 4928000 | |
ADD | Cost incurred during the year | 2581000 | 2347000 | 3049200 |
Total cost incurred till date | 2581000 | 4928000 | 7977200 | |
ADD | Estimated cost to be incurred | 6319000 | 2772000 | 0 |
Total estimated cost to be incurred | 8900000 | 7700000 | 7977200 | |
Percentage of completion (A) | 29% | 64% | 100% | |
(cost incurred till date /total estimated cost ) | ||||
Total revenue (B) | 10000000 | 10000000 | 10000000 | |
Total revenue recognized (A *B) | 2900000 | 6400000 | 10000000 | |
Less | Revenue recognized in previous year | 0 | 2900000 | 6400000 |
revenue recognized in current year | 2900000 | 3500000 | 3600000 | |
2018 | 2019 | 2020 | ||
Revenue | 2900000 | 3500000 | 3600000 | |
Less | Cost incurred | 2581000 | 2347000 | 3049200 |
Gross profit | 319000 | 1153000 | 550800 | |
2018 | ||||
1 | Construction in progress | 2581000 | ||
Accounts payable | 2581000 | |||
2 | Contracts receivable | 2090000 | ||
Progress billings | 2090000 | |||
3 | Construction in progress | 319000 | ||
Construction expense | 2581000 | |||
Construction revenue | 2900000 | |||
4 | Cash | 1845000 | ||
Contract receivable | 1845000 | |||
2019 | ||||
1 | Construction in progress | 2347000 | ||
Accounts payable | 2347000 | |||
2 | Contracts receivable | 2838000 | ||
Progress billings | 2838000 | |||
3 | Construction expense | 2347000 | ||
Construction on progress | 1153000 | |||
Construction revenue | 3500000 | |||
4 | Cash | 2900000 | ||
Contract receivable | 2900000 | |||
2020 | ||||
1 | Construction in progress | 3049200 | ||
Accounts payable | 3049200 | |||
2 | Contracts receivable | 5072000 | ||
Progress billings | 5072000 | |||
3 | Construction expense | 3049200 | ||
Construction on progress | 550800 | |||
Construction revenue | 3600000 | |||
4 | Cash | 5255000 | ||
Contract receivable | 5255000 | |||
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....
in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,074,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,542,000 5,658,000 2,020,000 1,810,000 2019 $3,772,000 1,886,000 4,294,000 3,800,000 3,686,000 4,390,000 Westgate recognizes revenue over time according to percentage of completion....
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000 Westgate recognizes revenue over time according to percentage of completion....
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the year 1,870,000 3,200,000 4,930,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...