Question

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018 2019 2020
Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200
Estimated costs to complete as of year-end 6,319,000 2,772,000 0
Billings during the year 2,090,000 2,838,000 5,072,000
Cash collections during the year 1,845,000 2,900,000 5,255,000

Westgate recognizes revenue over time according to percentage of completion.

2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).

Then Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract.

Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2018 2019 2020
Cost incurred during the year $ 2,581,000 $ 3,845,000 $ 3,245,000
Estimated costs to complete as of year-end 6,319,000 3,145,000 0

Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2018 2019 2020
Cost incurred during the year $ 2,581,000 $ 3,845,000 $ 4,035,000
Estimated costs to complete as of year-end 6,319,000 4,190,000 0
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Percentage completion method 2018 2019 2020
Cost incurred in till previous year 0 2581000 4928000
ADD Cost incurred during the year 2581000 2347000 3049200
Total cost incurred till date 2581000 4928000 7977200
ADD Estimated cost to be incurred 6319000 2772000 0
Total estimated cost to be incurred 8900000 7700000 7977200
Percentage of completion (A) 29% 64% 100%
(cost incurred till date /total estimated cost )
Total revenue (B) 10000000 10000000 10000000
Total revenue recognized (A *B) 2900000 6400000 10000000
Less Revenue recognized in previous year 0 2900000 6400000
revenue recognized in current year 2900000 3500000 3600000
2018 2019 2020
Revenue 2900000 3500000 3600000
Less Cost incurred 2581000 2347000 3049200
Gross profit 319000 1153000 550800
2018
1 Construction in progress 2581000
               Accounts payable 2581000
2 Contracts receivable 2090000
               Progress billings 2090000
3 Construction in progress 319000
Construction expense 2581000
               Construction revenue 2900000
4 Cash 1845000
          Contract receivable 1845000
2019
1 Construction in progress 2347000
               Accounts payable 2347000
2 Contracts receivable 2838000
               Progress billings 2838000
3 Construction expense 2347000
Construction on progress 1153000
               Construction revenue 3500000
4 Cash 2900000
          Contract receivable 2900000
2020
1 Construction in progress 3049200
               Accounts payable 3049200
2 Contracts receivable 5072000
               Progress billings 5072000
3 Construction expense 3049200
Construction on progress 550800
               Construction revenue 3600000
4 Cash 5255000
          Contract receivable 5255000
Add a comment
Know the answer?
Add Answer to:
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa ...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....

  • in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,074,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,542,000 5,658,000 2,020,000 1,810,000 2019 $3,772,000 1,886,000 4,294,000 3,800,000 3,686,000 4,390,000 Westgate recognizes revenue over time according to percentage of completion....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000 Westgate recognizes revenue over time according to percentage of completion....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the year 1,870,000 3,200,000 4,930,000 Westgate recognizes revenue over time according to...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT