In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,581,000 | $ | 2,347,000 | $ | 3,049,200 | |||
Estimated costs to complete as of year-end | 6,319,000 | 2,772,000 | 0 | ||||||
Billings during the year | 2,090,000 | 2,838,000 | 5,072,000 | ||||||
Cash collections during the year | 1,845,000 | 2,900,000 | 5,255,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
(Do not round intermediate calculations and round your
final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.)
2021 | 2022 | 2023 | |||||||
Costs incurred during the year | $ | 2,581,000 | $ | 3,845,000 | $ | 3,245,000 | |||
Estimated costs to complete as of year-end | 6,319,000 | 3,145,000 | 0 | ||||||
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $3,849,200 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,581,000 6,319,000 2,890,000 1,845,000 2022 $2,347,000 2,772,000 2,838,000 2,900,000 5,072,000 5,255,000...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 4....
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 2023 $2,008,600 0 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. Problem...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008, 600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion....
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,550,000 $4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during the year 2,050,000 4,750,000 3,200,000 Cash collections during the year 1,825,000 4,100,000 4,075,000 Westgate recognizes revenue over time according to percentage of...