Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June...
Exercise 5-18 Long-term contract; revenue recognition over time vs. upon project completion [LO5-9] On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.ะก., for $270 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 $ 50 $100 60...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $400 million. The expected completion date is April 1, 2023. just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 60 $130 $55...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 70 $ 110 $ 80 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 70 130 Costs incurred during the year Estimated costs to complete as of December 31 2022 $60 30...
Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000...
On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $350 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows (5 in millions): 2021 $ 3e 170 Costs incurred during the year Estimated costs to complete as of December 31 2022 $142 0...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...