Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO6-8, 6-9]
On February 1, 2021, Arrow Construction Company entered into a
three-year construction contract to build a bridge for a price of
$8,125,000. During 2021, costs of $2,050,000 were incurred, with
estimated costs of $4,050,000 yet to be incurred. Billings of
$2,560,000 were sent, and cash collected was $2,300,000.
In 2022, costs incurred were $2,560,000 with remaining costs
estimated to be $3,675,000. 2022 billings were $2,810,000, and
$2,525,000 cash was collected. The project was completed in 2023
after additional costs of $3,850,000 were incurred. The company’s
fiscal year-end is December 31. This project does not qualify for
revenue recognition over time.
Required:
1. Calculate the amount of revenue and gross
profit or loss to be recognized in each of the three years.
2a. Prepare journal entries for 2021 to record the
transactions described (credit "various accounts" for construction
costs incurred).
2b. Prepare journal entries for 2022 to record the
transactions described (credit "various accounts" for construction
costs incurred).
3a. Prepare a partial balance sheet to show the
presentation of the project as of December 31, 2021.
3b. Prepare a partial balance sheet to show the
presentation of the project as of December 31, 2022
Part 1
Year |
Revenue recognized |
Gross profit (loss) recognized |
2021 |
0 |
0 |
2022 |
0 |
(160000) |
2023 |
8125000 |
(175000) |
Total |
8125000 |
$(335000) |
Total loss = Total cost – total revenue = (2050000+2560000+3850000)-8125000 = 335000
Loss 2023 = additional costs 2023 - remaining costs estimated 2022 = 3850000-3675000 = 175000
Loss 2022 = total loss – loss 2023 = 335000-175000 = 160000
Part 2-a
No |
Year |
General journal |
Debit |
Credit |
1 |
2021 |
Construction in progress |
2050000 |
|
Various accounts |
2050000 |
|||
2 |
2021 |
Accounts receivable |
2560000 |
|
Billings |
2560000 |
|||
3 |
2021 |
Cash |
2300000 |
|
Accounts receivable |
2300000 |
|||
4 |
2021 |
No journal entry required |
Part 2-b
No |
Year |
General journal |
Debit |
Credit |
1 |
2022 |
Construction in progress |
2560000 |
|
Various accounts |
2560000 |
|||
2 |
2022 |
Accounts receivable |
2810000 |
|
Billings |
2810000 |
|||
3 |
2022 |
Cash |
2525000 |
|
Accounts receivable |
2525000 |
|||
4 |
2022 |
Loss on long-term contract |
160000 |
|
Construction in progress |
160000 |
Part 3-a
Balance Sheet (Partial) At December 31, 2021 |
|
Current assets: |
|
Accounts receivable |
260000 |
Current liabilities: |
|
Billings in excess of costs |
510000 |
Part 3-b
Balance Sheet (Partial) At December 31, 2022 |
|
Current assets: |
|
Accounts receivable |
545000 |
Current liabilities: |
|
Billings in excess of costs less loss (2560000+2810000)-(2050000+2560000-(160000)) |
920000 |
Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO6-8,...
Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2,130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2,630,000 with remaining costs estimated to be $3,795,000. 2022 billings were $2,880,000...
Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project (LO6-9) On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,270,000. During 2021, costs of $2,090,000 were incurred with estimated costs of $4,090,000 yet to be incurred. Billings of $2,590,000 were sent, and cash collected was $2,340,000. points eBook In 2022, costs incurred were $2,590,000 with remaining costs estimated to be $3,735,000. 2022 billings...
Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
262020 10. Anard 2.00 points 20 Long-term contract; revenue recognition upon project completion loss projected on entire Exercise 5 project |LOS-8,5-9) Arrow Construction Company entered into a three-year construction On February 10 costs of $2.170.000 were incurred, with estimated costs of 4170 000 yet to be incurred B.ings of to b e a bridge for a price of 704000 were sent and cash collected was 32,420.000 we were $2.704,000 with remaining costs mased to be $3.855 000. 2019 ings were...
Saved Help Save & Exit Submit Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project (LO6-9) On February 1, 2021, Arrow Construction Company entered into a three year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2,630,000 with remaining costs estimated...
omework Saved Help Save & Exit Submit Check my work Exercise 5-19 Long-term contract; revenue recognition over time; loss projected on entire project [LO5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,180,000. During 2018, costs of $2,060,000 were incurred with estimated costs of $4,060,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,310,000. In 2019, costs incurred were $2,560,000 with remaining...
Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,976,000 5, 624,000 1,600,000 1,400,000 2022 $3,420,000 2,204,000 3,796,000 3,200,000 2023 $2,424, 400 0...
Exercise 6-19 (Algo) Long-term contract; revenue recognition over time and at a point in time [LO6-9] Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,750,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2022 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2021 $ 360,000 1,440,000 500,000 445,000 2022 $2,155,000 0 1,770,000 1,825,000...