Question

262020 10. Anard 2.00 points 20 Long-term contract; revenue recognition upon project completion loss projected on entire Exer
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Arrow Construction Company
Ans to 1 Calculation of Gross Profit
Particulars 2018 2019 2020 Note
Contract Price          8,425,000          8,425,000          8,425,000 A
Cost Incurred during the year          2,170,000    2,704,000.00          3,970,000 B
Estimated cost to complete          4,170,000          3,855,000                        -   C
Cost Incurred to date          2,170,000          4,874,000          8,844,000 D
(Sum total of the cost incurred during the year)
Estimated total cost          6,340,000          8,729,000          8,844,000 E=C+D
Percentage complete 34.23% 55.84% 100.00% F=D/E
(Cost Incurred to date/Estimated total cost)
Revenue to be recognized          2,883,636          1,820,620          3,720,744 G
(Contract Price*Percentage complete)- revenue previously recognized
Year 2018: 34.23% completed. Revenue recognized = 34.23% x $ 8,425,000 = $ 2,883,636.
Year 2019: 55.84% completed. Revenue recognized = 55.84% x $ 8,425,000 – $ 2,883,636 (previously recognized) = $ 1,820,620.
Year 2020: 100% completed. Revenue recognized = 100% x $ 8,425,000 – $ 2,883,636- $ 1,820,620 (previously recognized) = $ 3,720,744.
Gross Profit/(Loss)             713,636           (883,380)            (249,256) H=G-B
Billings during the year    2,704,000.00    2,954,000.00
Collection during the year    2,420,000.00    2,645,000.00
2018 2019
Ans to 2a and 2b Journal Entries Debit $ Credit $ Debit $ Credit $
Costs Incurred CIP (Work-in-progress)    2,170,000 2,704,000
Cash    2,170,000     2,704,000
Billing Accounts Receivable    2,704,000 2,954,000
Billing on CIP    2,704,000     2,954,000
Receiving Payments Cash    2,420,000 2,645,000
Accounts Receivable    2,420,000     2,645,000
Period end adjustments for Revenue Construction Expense    2,170,000
(Gross Profit entry) CIP (Work-in-progress)       713,636
Construction Revenue    2,883,636
Period end adjustments for Revenue Construction Expense 2,704,000
(Gross Profit entry) CIP (Work-in-progress)        883,380
Construction Revenue     1,820,620
Workings for Balance Sheet
CIP (Work-in-progress)
Account Amount ($)
Cash                                 2,170,000
Construction Revenue                                    713,636
Balance at the end of 2018                                 2,883,636
Cash                                 2,704,000
Construction Revenue                                   (883,380)
Balance at the end of 2019                                 4,704,256
Accounts Receivable
Account Amount ($)
Billing on CIP                                 2,704,000
Cash                                (2,420,000)
Balance at the end of 2018                                    284,000
Billing on CIP                                 2,954,000
Cash                                (2,645,000)
Balance at the end of 2019                                    593,000
Billing on CIP
Account Amount ($)
Accounts Receivable                                 2,704,000
Balance at the end of 2018                                 2,704,000
Accounts Receivable                                 2,954,000
Balance at the end of 2019                                 5,658,000
Ans to 3a and 3b
Balance Sheet (Partial) 2018 2019
Current Assets:
CIP (Work-in-progress)          2,883,636          4,704,256
Accounts Receivable             284,000             593,000
        3,167,636         5,297,256
Current Liabilities:
Billing on CIP    2,704,000.00    5,658,000.00
2,704,000.00 5,658,000.00
Add a comment
Know the answer?
Add Answer to:
262020 10. Anard 2.00 points 20 Long-term contract; revenue recognition upon project completion loss projected on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Award 2.00 points Exercise 5-19 Long-term 6.19 Long-term contract, revenue recognition over time, loss projected on...

    Award 2.00 points Exercise 5-19 Long-term 6.19 Long-term contract, revenue recognition over time, loss projected on entire project ILO5-91 do g s of Construction Company entered in On February a threeyear construction contrat a of $2.200.000 were incurred with estimated cost of $4 200.000 yet is bein 2 450 000 0 000 w esent and cash cobacted $2.700 000 with remaining cost estimated to be 53.000.000 2019 In 2018, concurrer a proct was completed in 2020 aterational costs of 14...

  • Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO6-8,...

    Exercise 6-22 (Algo) Long-term contract; revenue recognition upon project completion; loss projected on entire project [LO6-8, 6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2021, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2022, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2022 billings...

  • Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project (LO6-9) On...

    Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project (LO6-9) On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,270,000. During 2021, costs of $2,090,000 were incurred with estimated costs of $4,090,000 yet to be incurred. Billings of $2,590,000 were sent, and cash collected was $2,340,000. points eBook In 2022, costs incurred were $2,590,000 with remaining costs estimated to be $3,735,000. 2022 billings...

  • Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On...

    Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000...

  • Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On...

    Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project [LO6-9] On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2,130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2,630,000 with remaining costs estimated to be $3,795,000. 2022 billings were $2,880,000...

  • omework Saved Help Save & Exit Submit Check my work Exercise 5-19 Long-term contract; revenue recognition...

    omework Saved Help Save & Exit Submit Check my work Exercise 5-19 Long-term contract; revenue recognition over time; loss projected on entire project [LO5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,180,000. During 2018, costs of $2,060,000 were incurred with estimated costs of $4,060,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,310,000. In 2019, costs incurred were $2,560,000 with remaining...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...

  • Saved Help Save & Exit Submit Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss...

    Saved Help Save & Exit Submit Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project (LO6-9) On February 1, 2021, Arrow Construction Company entered into a three year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2,630,000 with remaining costs estimated...

  • Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to...

    Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to build a bridge for a price of $8,200,000. During 2021, costs of $2,080,000 were incurred, with estimated costs of $4,080,000 yet to be incurred. Billings of $2,596,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,596,000 with remaining costs estimated to be $3.720.000. 2022 billings were $2,846,000, and $2,555,000 cash was collected. The project was completed in 2023 after additional...

  • Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] In 2021, the Westgate Construction Company...

    Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $1,976,000 5, 624,000 1,600,000 1,400,000 2022 $3,420,000 2,204,000 3,796,000 3,200,000 2023 $2,424, 400 0...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT