why the gross profit of 2014 is -766667
2013 | 2014 | 2015 | |
Actual costs to date | 2000000 | 4500000 | 8300000 |
Estimated costs to complete | 4000000 | 3600000 | 0 |
Total costs to complete | 6000000 | 8100000 | 8300000 |
Estimated gross profit for the project | 2000000 | -100000 | -300000 |
Percentage of completion | 33.33% | 55.56% | 100.00% |
Gross profit to date | 666667 | -100000 | -100000 |
Gross profit recognized in prior years | 0 | 666667 | 0 |
GP to be recognized during the year | 666667 | -766667 | -100000 |
Explanation: | |||
Losses are to be recognized in full; they are not to be prorated according to the % | |||
of completion. As the loss to date as at the end of 2014 was $100000, the GP | |||
accounted earlier has also to be withdrawn. Hence, loss for the year to be | |||
reccognized = 100000+666667 = 766667 | |||
That is GP = -$766,667 |
why the gross profit of 2014 is -766667 On February 1, 2013, Arrow Construction Company entered...
On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2.475,000 cash was collected. The project was completed in 2023 after additional costs of...
At the beginning of 2013, the Harding Construction Company received a contract to build an office building for $10 million. Harding will construct the building according to specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will bill the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2013 2014 2015 Cost incurred during the year $2,300,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,060,000 were incurred, with estimated costs of $4,060,000 yet to be incurred. Billings of $2,572,000 were sent, and cash collected was $2,310,000. In 2022, costs incurred were $2,572,000 with remaining costs estimated to be $3,690,000. 2022 billings were $2,822,000, and $2,535,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2021, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000. In 2022, costs incurred were $2,692,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,942,000, and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...