Question

Question6. Long-term contract based on percentage of completion method (32 (4) Prepare journal entry to record gross profit for 2017(6 points) (5) Show at end of 2017 and 2018, what are the balance af CIP ( points) points) lims Construction Co. has a $85,000,000 contract to build a new football stadium The project began on January 1, 2016 with an expected completion date of October 31, 2018. The following table provides infomation gathered during the construction period. Jim uses the percentage completion method to account for this contract 2016 2017 2018 2016 Construction costs incurred during the year Estimated costs to complete Billings during the year Cash collected duringyear 25,500,000 38,250,000 17,000,000 12,750,000 32,512,500 24862,500 29,750,000 24,852,500 BB CIP Construction costs incurred during the year Gross Profit EB CIP 38,250,000 42,500,000 (1) Prepare journal entry to record gross profit for 2016 (4 points) [2) Prepare all necessary journal entries for 2017 (7 points) (3) Atend of 2016 and 2017, what are the balance af CIP (6 points) BB CIP Construction costs incurred during the year Gross Profit EB CIP g2017, the costs and estimation have changed according to the following table 2016 2017 36,975,000 26,775,000 29,750,000 25,500,000 201 Construction costs incurred duringtheyar Estimated costs to complete Billings during the year Cash collected during year 25,500,000 26,775,000 38,250,000 17,000,000 12,750,000 38,250,000 42,500,000

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Question6. Long-term contract based on percentage of completion method (32 (4) Prepare journal entry to record...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2016, Pioneer Construction Company entered into a contract to construct a road for Denton County...

    In 2016, Pioneer Construction Company entered into a contract to construct a road for Denton County for S10,000,000. The road was completed in 2018. Information related to the contract is as follows: 2017 $2,610,000 S3,162,000 $2,230,800 2,028,000 2,100,000 3,672,000 4,228,000 1,850,000 3,000,000 5,150,000 2016 2018 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year 6,390,000 0 Cash collections during the year Pioneer recognizes revenue over time according to percentage of completion. Calculate the...

  • Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to...

    Question: Question:1.    When the percentage-of-completion method of accounting for long-term contracts, the percentage of completion used to recognize gross profit in the first year usually is determined by measuring: a. costs incurred in the first year, divided by estimated remaining costs to complete the project. b. costs incurred in the first year, divided by estimated total cost of the completed project. c. costs incurred in the first year, divided by estimated gross profit. d. none of the above.    2.As of...

  • 6 Problem 5-11 Long-term contract; revenue recognition upon completion [LO5-9) In 2018, the Westgate Construction Company...

    6 Problem 5-11 Long-term contract; revenue recognition upon completion [LO5-9) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $30,000000 The road was completed in 2020 Information related to the contract is as folows Billings during the year Cash cellections during the year 1,800,0003,690,84,600,0 SeferencesWestgate Construction uses the completed contract method of accounting for long-term construction contrects Required: 1. Calculate the amount of revenue and gross profit (oss) to be...

  • On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...

  • Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract...

    Tamarisk Construction Company uses the percentage-of-completion method of accounting. In 2017, Tamarisk began work under contract #E2-D2, which provided for a contract price of $2,227,000. Other details follow: 2017 2018 Cost incurred during the year $660240 $1422000 Estimated costs to complete, as of December 31 911760 0 Billings to date 425000 2227000 Collections during the year 347000 1523000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $______________ Revenue...

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started...

    Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:                                             2017                                    2018 Current year construction costs                                       $3,300,000                             $ 620,000 Estimated remaining costs to complete                              600,000                                   -0- Current year billings                                                            3,100,000                              1,400,000 Current year collections                                                    3,000,000                                1,500,000 Required: Calculate the following amounts for each method:               Completed Percentage-of Contract Completion                                   2017      2018    2017    2018 a) Gross Profit                                                                                              $             $           $          ...

  • Riverbed Construction Company uses the percentage-of-completion method of accounting. In 2017, Riverbed began work under contract...

    Riverbed Construction Company uses the percentage-of-completion method of accounting. In 2017, Riverbed began work under contract #E2-D2, which provided for a contract price of $2,195,000. Other details follow: 2017 2018 Costs incurred during the year $695,310 $1,404,000 Estimated costs to complete, as of December 31 921,690 –0– Billings to date 426,000 2,195,000 Collections during the year 352,000 1,475,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017 $ Revenue...

  • Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to...

    Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows:...

  • In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract...

    In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract price of $22,000,000. The estimated construction costs were $15,500,000. The project was completed on time during the 2917 year. The following information is available for the three year period of the construction project. 2015 2016 2017 Costs Incurred to Date $6,188,000 $12,360,000 $15,875,000 Estimated Costs to Complete 9,282,000 3,090,000 -- Billings to Date 6,400,000 18,890,000 22,000,000 Collections to Date 5,100,000 17,110,000 21,630,000 Required 1....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT