Question

1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred during year Estimated costs to complete at 12/31 20,500,000 4,500,000 12,075,0009,425,000 8,925,000 0 A. B. C. Determine the amount of Gross Profit that would be recognized each year under Percentage of Completion. What amount of Gross Profit would be recognized in 2017 if the estimated costs to complete were $11,000,000? What would be the amount of Gross Profit recognized each year if the completed Contract Method were used instead?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ques 1 Actual cost to date Estimated Costs (4500000+20500000) 4500000+12075000+8925000 % Completion 2016 2017 | (4500000-12075 000) 2018 4500000/ 18% 65% 100% Project Completes this vear 2016 2018 Year Contract price 2017 27,500,000$27,500,000 $ 27,500,000 26,000,000 26,000,000 1,500,000 Actual Cost to date Estimated costs to complete Total estimated costs 4,500,000$16,575,000 $ 20,500,000$8,925,000 $ 25,000,000$25,500,000 $ Estimated gross (actual in 2018) proft 2,500,000$2,000,000 $ 2016 Revenue Recognition Contract price(A) Percentage Completion(B) Cumulative revenue(A B Less:Revenue already recognised Construction Revenue Less:Actual Costs Gross Profit/loss) 2017 2018 27,500,000$27,500,000 $ 27,500,000 18% 65% 100% 4,950,00017,875,000 $ $(4,950,000) $ 4,950,00012,925,000 $ 4,500,000) $ (12,075,000)|$ 850,000 $ 27,500,000 (17,875,000) 9,625,000 9,425,000) 200,000 450,000 $Ques 2 Actual cost to date Estimated Costs 4500000+20500000 (4500000+12075000+11000000) % Completion 4500000 2016 2017 (4500000+12075000) 2018 18% 60% 100% Project Completes this year 2016 2017 2018 Contract price 27,500,000 $ 27,500,000 26,000,000 26,000,000 1,500,000 4,500,000 16,575,000 Actual Cost to date Estimated costs to complete Total estimated costs 20,500,000 11,000,000 S 25,000,000$27,575,000 $ 2,500,000$ Estimated gross proft (actual in 2018 Revenue Recognition Contract price(A) Percentage Completion (B) Cumulative revenue(A B) Less Revenue already recognised Construction Revenue Less:Actual Costs Gross Profit/(loss) 2016 2017 2018 27,500,000 100% 27,500,000 16,529,918 10,970,082 9,425,000 1,545,082 27,500,00027,500,000 18% 60% 4,950,000$16,529,918$ 4,950,000) S 4,950,000$11,579,918 $ 4,500,000)$ (12,075,000) 450,000$ (495,082)SGross Revenue Pofit(Loss) Recognised Recognised Year 2016 S 2017 $- 2018 $27,500,000 $1,500,000 revenue is recognised only on completion

Ques 1 Actual cost to date Estimated Costs (4500000+20500000) 4500000+12075000+8925000 % Completion 2016 2017 | (4500000-12075 000) 2018 4500000/ 18% 65% 100% Project Completes this vear 2016 2018 Year Contract price 2017 27,500,000$27,500,000 $ 27,500,000 26,000,000 26,000,000 1,500,000 Actual Cost to date Estimated costs to complete Total estimated costs 4,500,000$16,575,000 $ 20,500,000$8,925,000 $ 25,000,000$25,500,000 $ Estimated gross (actual in 2018) proft 2,500,000$2,000,000 $ 2016 Revenue Recognition Contract price(A) Percentage Completion(B) Cumulative revenue(A B Less:Revenue already recognised Construction Revenue Less:Actual Costs Gross Profit/loss) 2017 2018 27,500,000$27,500,000 $ 27,500,000 18% 65% 100% 4,950,00017,875,000 $ $(4,950,000) $ 4,950,00012,925,000 $ 4,500,000) $ (12,075,000)|$ 850,000 $ 27,500,000 (17,875,000) 9,625,000 9,425,000) 200,000 450,000 $

Add a comment
Know the answer?
Add Answer to:
1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to...

    Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows:...

  • Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimated that the complex will take 3 years to construct. Additional information follows. Estimated cost of complex Contract price AA 600,000 900,000 The following data pertain to the construction period. 2019 610,000 $ 6100 A 2017 270,000 330,000 270,000 240,000 2018 450,000 150,000 550,000 500,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

  • Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $895,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $268,200 $482,760 $605,000 Estimated costs to complete 327,800 113,240 –0– Progress billings to date 267,000 552,000 895,000 Cash collected to date...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2020. lust in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2018 2019 2020 $ 60 $130 $70...

  • Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $246,000 354,000 270,000 240,000 2018 $432,000 168,000 546,000 496,000 2019 $612,000...

  • Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $266,640 339,360 270,000 240,000 2018 $412,080 193,920 545,000 495,000 $617,000...

  • 1) A construction company entered into a fixed-price contract to build an office building for $20...

    1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...

  • Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. I...

    Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2019 $608,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $294,000 306,000 268,000 238,000 2018 $432,000 168,000 547,000 497,000...

  • Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build...

    Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $263,120 334,880 273,000 2018 $460,460 137,540 556,000 506,000 2019...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT