Answer:(a) | |||
Particulars | 2017 | 2018 | 2019 |
Price(a) | 901000 | 901000 | 901000 |
Estimated costs: | |||
Cost to date | 246000 | 432000 | 612000 |
Estimated cost to complete | 354000 | 168000 | 0 |
Estimated total costs (b) | 600000 | 600000 | 612000 |
Estimated gross profit (a-b) | 301000 | 301000 | 289000 |
Gross Profit Recognized | |||
($246,000/$600,000) X $301,000 | 123410 | ||
($432,000/$600,000 X 301,000)- $123,410 | 93310 | ||
($123,410 + $93,310)=$289,000-$216,720 | 72280 |
Answer:(b)
2017 : $ -0- No gross profit would be recognized under completed-contract method.
2018 : $ -0- No gross profit would be recognized under completed-contract method.
2019 :
Total Price $901,000
Total Cost ($612,000)
Gross Profit recognized 2016 $289,000
Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $895,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $268,200 $482,760 $605,000 Estimated costs to complete 327,800 113,240 –0– Progress billings to date 267,000 552,000 895,000 Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2019 $608,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $294,000 306,000 268,000 238,000 2018 $432,000 168,000 547,000 497,000...
Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $266,640 339,360 270,000 240,000 2018 $412,080 193,920 545,000 495,000 $617,000...
Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $272,700 $466,620 $618,000 Estimated costs to complete 333,300 139,380 –0– Progress billings to date 273,000 546,000 902,000 Cash collected to date...
Pearl Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2020 2021 2022 $272,700 $466,620 $618,000 333,300 139,380 -0- 273,000 546,000 902,000...
Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $263,120 334,880 273,000 2018 $460,460 137,540 556,000 506,000 2019...
Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimated that the complex will take 3 years to construct. Additional information follows. Estimated cost of complex Contract price AA 600,000 900,000 The following data pertain to the construction period. 2019 610,000 $ 6100 A 2017 270,000 330,000 270,000 240,000 2018 450,000 150,000 550,000 500,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $...
Pronghorn Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $894,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $274,160 $417,200 $607,000 Estimated costs to complete 321,840 178,800 –0– Progress billings to date 272,000 550,000 894,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $275,080 $412,620 $607,000 Estimated costs to complete 322,920 185,380 –0– Progress billings to date 272,000 545,000 897,000 Cash collected to date...