Cheyenne Construction Company has entered into a contract
beginning January 1, 2017, to build a parking complex. It has been
estimated that the complex will cost $596,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $895,000. The following data pertain to the construction
period.
2017 |
2018 |
2019 |
||||
Costs to date | $268,200 | $482,760 | $605,000 | |||
Estimated costs to complete | 327,800 | 113,240 | –0– | |||
Progress billings to date | 267,000 | 552,000 | 895,000 | |||
Cash collected to date | 237,000 | 502,000 | 895,000 |
(a) Using the percentage-of-completion method,
compute the estimated gross profit that would be recognized during
each year of the construction period. (If answer is 0,
please enter 0. Do not leave any fields
blank.)
Gross profit recognized in 2017 | $ | |
Gross profit recognized in 2018 | $ | |
Gross profit recognized in 2019 | $ |
(b) Using the completed-contract method, compute
the estimated gross profit that would be recognized during each
year of the construction period. (If answer is 0,
please enter 0. Do not leave any fields
blank.)
Gross profit recognized in 2017 | $ | |
Gross profit recognized in 2018 | $ | |
Gross profit recognized in 2019 | $ |
Revenue recognition as per Percentage of Completion Method - Cheyenne Cosntruction Company | ||||||||
Year | Actual cost incurred (A) | Total cost incurred till date (B) | Total estimated Cost ( C ) | % of completion (D= B/C) |
Contract Price (E ) |
Total Revenue to be recoganized (F=E * D) |
Revenue for current period (G) | Gross Profit (H=G-A) |
2017 | $268,200 | $268,200 | $596,000 | 45.00% | $895,000 | $402,750 | $402,750 | $134,550 |
(268200+327800) | ||||||||
2018 | $214,560 | $482,760 | $596,000 | 81.00% | $895,000 | $724,950 | $322,200 | $107,640 |
(482760+113240) | (724950-402750) | |||||||
2019 | $122,240 | $605,000 | $605,000 | 100.00% | $895,000 | $895,000 | 170050 | $47,810 |
(895000-724950) |
Revenue recognition as per Completed Contract method | |||||
Year | Actual cost incurred (A) | Total cost incurred till date (B) | Total estimated Cost ( C ) | Contract Price | Gross Profit |
(D) | |||||
2017 | $268,200 | $268,200 | $596,000 | $895,000 | $0 |
2018 | $214,560 | $482,760 | $596,000 | $895,000 | $0 |
2019 | $122,240 | $605,000 | $605,000 | $895,000 | $290,000.00 |
Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $246,000 354,000 270,000 240,000 2018 $432,000 168,000 546,000 496,000 2019 $612,000...
Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $266,640 339,360 270,000 240,000 2018 $412,080 193,920 545,000 495,000 $617,000...
Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2019 $608,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $294,000 306,000 268,000 238,000 2018 $432,000 168,000 547,000 497,000...
Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $263,120 334,880 273,000 2018 $460,460 137,540 556,000 506,000 2019...
Pronghorn Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $894,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $274,160 $417,200 $607,000 Estimated costs to complete 321,840 178,800 –0– Progress billings to date 272,000 550,000 894,000 Cash collected to date...
Bonita Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2020 $256,280 339,720 270,000 240,000 2021 $429,120 166,880 555,000 505,000 2022 $606,000...
Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimated that the complex will take 3 years to construct. Additional information follows. Estimated cost of complex Contract price AA 600,000 900,000 The following data pertain to the construction period. 2019 610,000 $ 6100 A 2017 270,000 330,000 270,000 240,000 2018 450,000 150,000 550,000 500,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $...
Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $272,700 $466,620 $618,000 Estimated costs to complete 333,300 139,380 –0– Progress billings to date 273,000 546,000 902,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $275,080 $412,620 $607,000 Estimated costs to complete 322,920 185,380 –0– Progress billings to date 272,000 545,000 897,000 Cash collected to date...