Question

Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimaCalculation of gross profit to be recognized in each year: 2017: X Estimated total gross profit = Gross profit for 2017 Costs(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a)

Description 2017 2018 2019
Contract price $        9,00,000 $        9,00,000 $        9,00,000
Costs to date $        2,70,000 $        4,50,000 $        6,10,000
Estimated costs to complete $        3,30,000 $        1,50,000
Estimated total costs $        6,00,000 $        6,00,000 $        6,10,000
Estimated gross profit $        3,00,000 $        3,00,000 $        2,90,000
2017
Gross profit for 2017
Costs to date x Estimated total gross profit
Estimated total costs
=270000/600000*300000
Gross profit $ 1,35,000
2018
Gross profit for 2018
Costs to date x Estimated total gross profit - Gross profit recognized until the end of the previous year
Estimated total costs
=(450000/600000) x 300000 - 135000
Gross profit $ 90,000
2019
Gross profit for 2019
Costs to date x Estimated total gross profit - Gross profit recognized until the end of the previous year
Estimated total costs
=(610000/610000) x 290000 - 225000
Gross profit $ 65,000

(b)

2017 Total Contract price = 0
Total Contract costs = 0
Total Gross profit       = 0
2018 Total Contract price = 0
Total Contract costs = 0
Total Gross profit       = 0
2019 Total Contract price = $        9,00,000
Total Contract costs = $        6,10,000
Total Gross profit       = $        2,90,000
Add a comment
Know the answer?
Add Answer to:
Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $246,000 354,000 270,000 240,000 2018 $432,000 168,000 546,000 496,000 2019 $612,000...

  • Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $266,640 339,360 270,000 240,000 2018 $412,080 193,920 545,000 495,000 $617,000...

  • Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $895,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $268,200 $482,760 $605,000 Estimated costs to complete 327,800 113,240 –0– Progress billings to date 267,000 552,000 895,000 Cash collected to date...

  • Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. I...

    Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2019 $608,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $294,000 306,000 268,000 238,000 2018 $432,000 168,000 547,000 497,000...

  • Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build...

    Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $263,120 334,880 273,000 2018 $460,460 137,540 556,000 506,000 2019...

  • Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...

  • Grouper Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Grouper Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2020 2021 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $266,640 339,360 270,000 240,000 $412,080 193,920 545,000 495,000 2022 $617,000...

  • Bonita Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Bonita Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2020 $256,280 339,720 270,000 240,000 2021 $429,120 166,880 555,000 505,000 2022 $606,000...

  • Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $266,640 339,360 270,000 240,000 2018 $412,080 193,920 545,000 495,000 $617,000...

  • Whispering Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Whispering Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT