(a)
Description | 2017 | 2018 | 2019 |
Contract price | $ 9,00,000 | $ 9,00,000 | $ 9,00,000 |
Costs to date | $ 2,70,000 | $ 4,50,000 | $ 6,10,000 |
Estimated costs to complete | $ 3,30,000 | $ 1,50,000 | |
Estimated total costs | $ 6,00,000 | $ 6,00,000 | $ 6,10,000 |
Estimated gross profit | $ 3,00,000 | $ 3,00,000 | $ 2,90,000 |
2017 | |||||
Gross profit for 2017 | |||||
Costs to date | x | Estimated total gross profit | |||
Estimated total costs | |||||
=270000/600000*300000 | |||||
Gross profit | $ 1,35,000 | ||||
2018 | |||||
Gross profit for 2018 | |||||
Costs to date | x | Estimated total gross profit | - | Gross profit recognized until the end of the previous year | |
Estimated total costs | |||||
=(450000/600000) | x | 300000 | - | 135000 | |
Gross profit | $ 90,000 | ||||
2019 | |||||
Gross profit for 2019 | |||||
Costs to date | x | Estimated total gross profit | - | Gross profit recognized until the end of the previous year | |
Estimated total costs | |||||
=(610000/610000) | x | 290000 | - | 225000 | |
Gross profit | $ 65,000 |
(b)
2017 | Total Contract price = | 0 |
Total Contract costs = | 0 | |
Total Gross profit = | 0 | |
2018 | Total Contract price = | 0 |
Total Contract costs = | 0 | |
Total Gross profit = | 0 | |
2019 | Total Contract price = | $ 9,00,000 |
Total Contract costs = | $ 6,10,000 | |
Total Gross profit = | $ 2,90,000 |
Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $246,000 354,000 270,000 240,000 2018 $432,000 168,000 546,000 496,000 2019 $612,000...
Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $266,640 339,360 270,000 240,000 2018 $412,080 193,920 545,000 495,000 $617,000...
Cheyenne Construction Company has entered into a contract
beginning January 1, 2017, to build a parking complex. It has been
estimated that the complex will cost $596,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $895,000. The following data pertain to the construction
period.
2017
2018
2019
Costs to date
$268,200
$482,760
$605,000
Estimated costs to
complete
327,800
113,240
–0–
Progress billings to
date
267,000
552,000
895,000
Cash collected to date...
Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2019 $608,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $294,000 306,000 268,000 238,000 2018 $432,000 168,000 547,000 497,000...
Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $263,120 334,880 273,000 2018 $460,460 137,540 556,000 506,000 2019...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Grouper Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2020 2021 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $266,640 339,360 270,000 240,000 $412,080 193,920 545,000 495,000 2022 $617,000...
Bonita Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2020 $256,280 339,720 270,000 240,000 2021 $429,120 166,880 555,000 505,000 2022 $606,000...
Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $266,640 339,360 270,000 240,000 2018 $412,080 193,920 545,000 495,000 $617,000...
Whispering Construction Company has entered into a contract
beginning January 1, 2020, to build a parking complex. It has been
estimated that the complex will cost $599,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $905,000. The following data pertain to the construction
period.
2020
2021
2022
Costs to date
$257,570
$413,310
$609,000
Estimated costs to complete
341,430
185,690
–0–
Progress billings to date
270,000
551,000
905,000
Cash collected to date...