Question

Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been esAyayai Company sells total outdoor grilling solutions, providing gas and charcoal grills, accessories, and installation serviThe State of Kentucky is planning major renovations in its parks during 2017 and enters into a contract with Ayayai to purchaAyayai sells its specialty combination gas/wood-fired grills to local restaurants. Each grill is sold for $1,000 (cost $523)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Swifty Construction Company

(a) Percentage-of-completion method:

Gross profit recognized in 2017 127600
Gross profit recognized in 2018 69600
Gross profit recognized in 2019 81800

Working:

2017 2018 2019
Costs incurred to date (a) 266640 412080 617000
Estimated additional costs to complete (b) 339360 193920 0
Estimated total costs (c) = (a) + (b) 606000 606000 617000
Percentage of completion (d) = (a)/(c) 44% 68% 100%
Revenue recognized to date (e) = (d) x $896000 394240 609280 896000
Revenue recognized during the year 394240 215040 286720
Less: Costs incurred during the year 266640 145440 204920
Gross profit for the year 127600 69600 81800

(b) Completed-contract method:

Gross profit recognized in 2017 0
Gross profit recognized in 2018 0
Gross profit recognized in 2019 279000

Under the completed contract method, the entire gross profit will be recognized in 2019 when the contract is completed.

Gross profit = Revenue - Actual costs incurred = $896000 - $617000 = $279000

Per HOMEWORKLIB RULES the first question has been answered. Please post each of the remaining independent questions separately. Thank you.

Add a comment
Know the answer?
Add Answer to:
Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $266,640 339,360 270,000 240,000 2018 $412,080 193,920 545,000 495,000 $617,000...

  • Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $246,000 354,000 270,000 240,000 2018 $432,000 168,000 546,000 496,000 2019 $612,000...

  • Grouper Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Grouper Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2020 2021 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $266,640 339,360 270,000 240,000 $412,080 193,920 545,000 495,000 2022 $617,000...

  • Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimated that the complex will take 3 years to construct. Additional information follows. Estimated cost of complex Contract price AA 600,000 900,000 The following data pertain to the construction period. 2019 610,000 $ 6100 A 2017 270,000 330,000 270,000 240,000 2018 450,000 150,000 550,000 500,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $...

  • Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $895,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $268,200 $482,760 $605,000 Estimated costs to complete 327,800 113,240 –0– Progress billings to date 267,000 552,000 895,000 Cash collected to date...

  • Cullumber Company sells total outdoor grilling solutions, providing gas and charcoal grills, accessories, and installation services...

    Cullumber Company sells total outdoor grilling solutions, providing gas and charcoal grills, accessories, and installation services for custom patio grilling stations. Respond to the requirements related to the following independent revenue arrangements for Cullumber products and services. Click here to view factor table. Cullumber offers contract GM205, which is comprised of a free-standing gas grill for small patio use plus installation to a customer's gas line for a total price $737. On a standalone basis, the grill sells for $637...

  • Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. I...

    Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2019 $608,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $294,000 306,000 268,000 238,000 2018 $432,000 168,000 547,000 497,000...

  • Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $272,700 $466,620 $618,000 Estimated costs to complete 333,300 139,380 –0– Progress billings to date 273,000 546,000 902,000 Cash collected to date...

  • Pronghorn Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Pronghorn Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $894,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $274,160 $417,200 $607,000 Estimated costs to complete 321,840 178,800 –0– Progress billings to date 272,000 550,000 894,000 Cash collected to date...

  • Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT