Question

Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution a:

Computation of % of completion, revenue recognition and Gross Profit - Sheridan construction company
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G - A)
2017 $263,120 $263,120 $598,000 44.00% $897,000 $394,680 $394,680 $131,560
2018 $197,340 $460,460 $598,000 77.00% $897,000 $690,690 $296,010 $98,670
2019 $148,540 $609,000 $609,000 100.00% $897,000 $897,000 $206,310 $57,770

Solution b:

Computation of Gross Profit - Revenue on completion - Sheridan Construction Company
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2017 $263,120 $263,120 $598,000 $897,000 $0
2018 $197,340 $460,460 $598,000 $897,000 $0
2019 $148,540 $609,000 $609,000 $897,000 $288,000
Add a comment
Know the answer?
Add Answer to:
Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $275,080 $412,620 $607,000 Estimated costs to complete 322,920 185,380 –0– Progress billings to date 272,000 545,000 897,000 Cash collected to date...

  • Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $895,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $268,200 $482,760 $605,000 Estimated costs to complete 327,800 113,240 –0– Progress billings to date 267,000 552,000 895,000 Cash collected to date...

  • Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Ayayai Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $246,000 354,000 270,000 240,000 2018 $432,000 168,000 546,000 496,000 2019 $612,000...

  • Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Swifty Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $266,640 339,360 270,000 240,000 2018 $412,080 193,920 545,000 495,000 $617,000...

  • Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. I...

    Sheffield Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2019 $608,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $294,000 306,000 268,000 238,000 2018 $432,000 168,000 547,000 497,000...

  • Problem 18-09 Shamrock Construction Company has entered into a contract beginning January 1, 2020, to build...

    Problem 18-09 Shamrock Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $601,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $270,450 $492,820 $613,000 Estimated costs to complete 330,550 108,180 –0– Progress billings to date 273,000 550,000 903,000 Cash collected...

  • Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $272,700 $466,620 $618,000 Estimated costs to complete 333,300 139,380 –0– Progress billings to date 273,000 546,000 902,000 Cash collected to date...

  • Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...

  • Pearl Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Pearl Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2020 2021 2022 $272,700 $466,620 $618,000 333,300 139,380 -0- 273,000 546,000 902,000...

  • Whispering Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Whispering Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT