Question

On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washin
Percentages of completion Choose numerator + Choose denominator = % complete to date 2018 2019 2020 + + = = 100.00% 2018 Reco
Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Suppose the estimated cos
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Requirement 1
% complete             = Actual Cost to date
Estimated Total Cost
Cost incurred during the year + Cost incurred in previous years = Actual Cost to date
2018 $                                                       60 + $                                 -   = $                   60
2019 $                                                     130 + $                                 60 = $                190
2020 $                                                       70 + $                               190 = $                260
Actual Cost to date + Estimated remaining costs = Estimated Total Cost
2018 $                                                       60 + $                                        190 = $                250
2019 $                                                     190 + $                                          60 = $                250
2020 $                                                     260 + $                                           -   = $                260
Percentages of Completion
Choose numerator ÷ Choose denominator = % complete to date
Actual Cost to date Estimated Total Cost
2018 $                                                       60 ÷ $                                        250 = 24.00%
2019 $                                                     190 ÷ $                                        250 = 76.00%
2020 100.00%
Contract Price × % complete to date = Construction revenue
2018 $                                                     390 × 24.00% = $94
2019 $                                                     390 × 76.00% = $296
2020 $                                                     390 × 100.00% = $390
2018
To date Recognized in prior years Recognized in 2018
Construction revenue $                94 $                -   $                                        94
Construction expense $                60 $                -   $                                        60
Gross Profit (loss) $                34 $                -   $                                        34
2019
To date Recognized in prior years Recognized in 2019
Construction revenue $              296 $               94 $                                     202
Construction expense $              190 $               60 $                                     130
Gross Profit (loss) $              106 $               34 $                                        72
2020
To date Recognized in prior years Recognized in 2020
Construction revenue $              390 $             296 $                                        94
Construction expense $              260 $             190 $                                        70
Gross Profit (loss) $              130 $             106 $                                        24
Requirement 3
Actual Cost to date + Estimated remaining costs = Estimated Total Cost
2018 $                                                       60 + $                                        190 = $                250
2019 $                                                     190 + $                                        190 = $                380
Percentage of completion
Choose numerator ÷ Choose denominator = % complete to date
Actual Cost to date Estimated Total Cost
2018 $                                                       60 ÷ $                                        250 = 24.00%
2019 $                                                     190 ÷ $                                        380 = 50.00%
Contract Price × % complete to date = Construction revenue
2018 $                                                     390 × 24.00% = $94
2019 $                                                     390 × 50.00% = $195
2018
To date Recognized in prior years Recognized in 2018
Construction revenue $                94 $                                        94
Construction expense $                60 $                                        60
Gross Profit (loss) $                34 $                                        34
2019
To date Recognized in prior years Recognized in 2019
Construction revenue $195 $94 $101
Construction expense $190 $60 $130
Gross Profit (loss) $5 $34 -$29

Feel free to ask any clarification, if required. Kindly provide feedback by thumbs up, if satisfied. It will be highly appreciated.
Thank you.

Add a comment
Know the answer?
Add Answer to:
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $400 million. The expected completion date is April 1, 2023. just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 60 $130 $55...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 70 $ 110 $ 80 Estimated costs to complete as of...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 60 $ 120 $ 70 Estimated costs to complete as of...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 70 130 Costs incurred during the year Estimated costs to complete as of December 31 2022 $60 30...

  • 7 On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a...

    7 On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 0.5 points 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 120...

  • Exercise 5-18 Long-term contract; revenue recognition over time vs. upon project completion [LO5-9] On June 15,...

    Exercise 5-18 Long-term contract; revenue recognition over time vs. upon project completion [LO5-9] On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.С., for $270 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 $ 50 $100 60...

  • On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $350 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows (5 in millions): 2021 $ 3e 170 Costs incurred during the year Estimated costs to complete as of December 31 2022 $142 0...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT