Requirement 1 | ||||||
% complete = | Actual Cost to date | |||||
Estimated Total Cost | ||||||
Cost incurred during the year | + | Cost incurred in previous years | = | Actual Cost to date | ||
2018 | $ 60 | + | $ - | = | $ 60 | |
2019 | $ 130 | + | $ 60 | = | $ 190 | |
2020 | $ 70 | + | $ 190 | = | $ 260 | |
Actual Cost to date | + | Estimated remaining costs | = | Estimated Total Cost | ||
2018 | $ 60 | + | $ 190 | = | $ 250 | |
2019 | $ 190 | + | $ 60 | = | $ 250 | |
2020 | $ 260 | + | $ - | = | $ 260 | |
Percentages of Completion | ||||||
Choose numerator | ÷ | Choose denominator | = | % complete to date | ||
Actual Cost to date | Estimated Total Cost | |||||
2018 | $ 60 | ÷ | $ 250 | = | 24.00% | |
2019 | $ 190 | ÷ | $ 250 | = | 76.00% | |
2020 | 100.00% | |||||
Contract Price | × | % complete to date | = | Construction revenue | ||
2018 | $ 390 | × | 24.00% | = | $94 | |
2019 | $ 390 | × | 76.00% | = | $296 | |
2020 | $ 390 | × | 100.00% | = | $390 | |
2018 | ||||||
To date | Recognized in prior years | Recognized in 2018 | ||||
Construction revenue | $ 94 | $ - | $ 94 | |||
Construction expense | $ 60 | $ - | $ 60 | |||
Gross Profit (loss) | $ 34 | $ - | $ 34 | |||
2019 | ||||||
To date | Recognized in prior years | Recognized in 2019 | ||||
Construction revenue | $ 296 | $ 94 | $ 202 | |||
Construction expense | $ 190 | $ 60 | $ 130 | |||
Gross Profit (loss) | $ 106 | $ 34 | $ 72 | |||
2020 | ||||||
To date | Recognized in prior years | Recognized in 2020 | ||||
Construction revenue | $ 390 | $ 296 | $ 94 | |||
Construction expense | $ 260 | $ 190 | $ 70 | |||
Gross Profit (loss) | $ 130 | $ 106 | $ 24 | |||
Requirement 3 | ||||||
Actual Cost to date | + | Estimated remaining costs | = | Estimated Total Cost | ||
2018 | $ 60 | + | $ 190 | = | $ 250 | |
2019 | $ 190 | + | $ 190 | = | $ 380 | |
Percentage of completion | ||||||
Choose numerator | ÷ | Choose denominator | = | % complete to date | ||
Actual Cost to date | Estimated Total Cost | |||||
2018 | $ 60 | ÷ | $ 250 | = | 24.00% | |
2019 | $ 190 | ÷ | $ 380 | = | 50.00% | |
Contract Price | × | % complete to date | = | Construction revenue | ||
2018 | $ 390 | × | 24.00% | = | $94 | |
2019 | $ 390 | × | 50.00% | = | $195 | |
2018 | ||||||
To date | Recognized in prior years | Recognized in 2018 | ||||
Construction revenue | $ 94 | $ 94 | ||||
Construction expense | $ 60 | $ 60 | ||||
Gross Profit (loss) | $ 34 | $ 34 | ||||
2019 | ||||||
To date | Recognized in prior years | Recognized in 2019 | ||||
Construction revenue | $195 | $94 | $101 | |||
Construction expense | $190 | $60 | $130 | |||
Gross Profit (loss) | $5 | $34 | -$29 |
Feel free to ask any clarification, if required. Kindly
provide feedback by thumbs up, if satisfied. It will be highly
appreciated.
Thank you.
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $400 million. The expected completion date is April 1, 2023. just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 60 $130 $55...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 70 $ 110 $ 80 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 60 $ 120 $ 70 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 70 130 Costs incurred during the year Estimated costs to complete as of December 31 2022 $60 30...
7 On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 0.5 points 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 120...
Exercise 5-18 Long-term contract; revenue recognition over time vs. upon project completion [LO5-9] On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.С., for $270 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 $ 50 $100 60...
On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $350 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows (5 in millions): 2021 $ 3e 170 Costs incurred during the year Estimated costs to complete as of December 31 2022 $142 0...